Good afternoon and welcome to Hallador Energy Company's third quarter 2026 earnings conference call. All participants are in a listen-only mode. A question-and-answer session will follow the prepared remarks. This call is being recorded. I will now turn the call over to Sean Mansouri with Elevate IR.

Sean MansouriInvestor Relations Advisor

Please proceed. Thank you, and good afternoon, everyone.

Sean MansouriInvestor Relations Advisor

We appreciate you joining us to discuss our third quarter 2026 results. With me today are Brent Bilsland, Chairman and Chief Executive Officer, and Todd Telesz, Chief Financial Officer. This afternoon, we released our third quarter 2026 financial and operating results in a press release that is now on the Hallador Investor Relations website. Today, we will discuss those results as well as our perspective on current market conditions. Following prepared remarks, we will open the call to answer your questions.

Sean MansouriInvestor Relations Advisor

Before we begin, a reminder that some of our remarks today include forward-looking statements, including statements about Turtle Creek, the final investment decision we are targeting, its cost and timing, interconnection and construction, long-term contracts for its output, and financing, refinancing, and a potential sale of an interest, our contracted forward sales, the availability and reliability of Merom, our estimates of the potential value of Turtle Creek, and market conditions, including demand for and pricing of power and capacity, all of which are subject to a variety of risks, uncertainties, and assumptions described in today's press release, our quarterly report on Form 10-Q for the quarter ended September 30, 2026, and our annual report on Form 10-K for 2025, each of which is available on our website and at sec.gov.

Sean MansouriInvestor Relations Advisor

While these forward-looking statements are based on information currently available to us, if one or more of these risks or uncertainties materialize, or if our underlying assumptions prove incorrect, actual results may vary materially from those we projected or expected, including because we do not yet have a signed offtake agreement for Turtle Creek, the interconnection agreement has not been executed, we have not secured commitments for the additional capital we will need, costs may exceed our estimates, or construction may be delayed, our debt requires a minimum return on repayment, Merom may not be available or reliable, our forward sales contracts include unit contingencies, volume options, and regulatory approvals, or market conditions change. Our estimates of the potential value of Turtle Creek and the goals and targets we discuss reflect management's current assumptions. They are not guidance or a prediction of our stock price.

Sean MansouriInvestor Relations Advisor

In providing these remarks, Hallador has no obligation to publicly update or revise any forward-looking statements, whether as a result of new information, future events, or otherwise, unless required by law to do so. With the preliminaries out of the way, I will turn the call over to Chairman and CEO, Brent Bilsland.

Brent BilslandChairman and CEO

Thank you, Sean, and good afternoon. Before we get into the details, there are three points from the quarter I want to highlight. First, Merom generated more than 1.4 million megawatt hours with one unit in maintenance outage for part of the quarter. Second, we made our third large Merom sale of the year with record capacity pricing. The capacity and energy pricing combined is over $80 per megawatt hour, and about 95% of Merom's accredited capacity is now sold through 2035 to investment-grade utilities. Third, we are working towards a final investment decision on Turtle Creek before the end of the year. Over the next 24 months, we will seek to roughly double an $800 million project into $1.6 billion of value, which we will walk you through further during the call.

Brent BilslandChairman and CEO

With those highlights in mind, we will cover five topics this afternoon: how Merom is running, how we are contracting it, where Turtle Creek stands, what comes next, how, where, and when we expect to create value, and how we intend to finance the remainder of Turtle Creek project. Todd will take you through the numbers. First, operations. Merom's uptime improved significantly during the quarter. As previously discussed, we took a major scheduled outage on one of the units at Merom in the second quarter. As planned, the outage ran into July, and when the unit came back, there were some teething issues, as you would expect after one of the largest maintenance outages we have ever performed. Once those resolved, both units ran well through the rest of the quarter.

Brent BilslandChairman and CEO

All said, Merom generated more than 1.4 million megawatt hours in the quarter with one unit in scheduled outage for part of it. For reference, our forward sales table assumes 5.2 million megawatt hours of annual generation. Energy prices are up roughly 20% this year, and the forward energy curve is up as well for the next several years. At those prices, the market is calling for Merom to run nearly all the time. The question at Merom is a simple one: How many hours each year are the units available? The market is valuing Merom's operation at a high price, and we are focused on investing in the plant to make it run as much as possible. At Merom, we focus on three things: people, plant, and process. Starting with people, we were fortunate to add several very talented operators to key management positions this year.

Brent BilslandChairman and CEO

Good operators want to work at a plant with a future, and Merom has one. Long-term contracts and an owner putting money into the machine and its reliability. When it comes to the second quarter, the planned maintenance outage was a big item on the list, and it's complete. We will keep investing in the plant's mechanical systems so the units are available more hours each year. On process, we're introducing AI tools to help our people see problems coming and find solutions sooner. This includes an operational AI tool that integrates real-time data to interpret and anticipate problems within the plant and provide proactive solutions that help reduce downtime. Our second topic is contracting. This year, we have had great success contracting Merom's output.

Brent BilslandChairman and CEO

We made large sales in March, May, and October, each priced higher than the one before, and the forward sales book now sits at about $3 billion, including half a billion of intercompany coal sales. The details are in the forward sales table in the October release and again in this afternoon's earnings release. About 95% of Merom's accredited capacity is under contract through 2035, and roughly two-thirds through 2040. Taking capacity and energy together, we're selling at $46 a megawatt hour for the rest of this year, $59 next year, $70 in 2029, and $75 from 2031 through 2035. That position provides revenue visibility subject to unit contingencies, volume options, and other terms described in our filings. These are the blended per megawatt hour figures in the forward sales table, which use the table's generation assumptions and include our estimates of energy revenue.

Brent BilslandChairman and CEO

The majority of those sales are with investment-grade utilities or carry a parent guarantee from one. Historically, these are very reliable agreements. We believe the credit risk in our book is low. Our revenue, therefore, largely depends on what we can control, keeping Merom available to run. As demand for electricity has grown, the prices we have contracted have risen with each sale, and we believe that gives us a good line of sight to development opportunities such as Turtle Creek. We are proud of this book, strong margins, investment-grade customers, and high-quality long-term contracts, all of which we believe are key differentiators for our company. We generally target selling about half of our output as unit contingent energy, a quarter as firm, and a quarter as merchant. Unit contingent means if a unit is down, we don't have to bid it into the day-ahead market.

Brent BilslandChairman and CEO

It also means we can take a unit down for maintenance without owing the market for power we aren't making. The exposure that remains is a unit that trips after we have committed it for the day, in which case we cover the balance of that day. That happened a few times this year and partially offset our results in the third quarter, and it's one more reason we're focused on increasing the reliability of Merom's hours. Unit contingent is lower risk than a firm sale, and it prices roughly at a 15% discount to firm energy. Let me describe the October agreement in some detail, because it shows what we mean by quality. The deal is about $700 million of capacity and energy over six years, beginning in 2029, at the highest capacity price we have contracted to date, more than 20% above the pricing we reported in March.

Brent BilslandChairman and CEO

Roughly $420 million of the $700 million is our estimate of unit-contingent energy revenue rather than a fixed commitment. Capacity and energy together, the price is over $80 per megawatt hour, the highest number on our forward sales table. I want to be very clear about one point. We sold to an investment-grade utility, not a data center. Data centers may be driving nearly all the growth in utility load, but our counterparty is an investment-grade utility that serves its whole territory, and it pays us whether any particular data center gets built or not. The energy sale is unit-contingent, and the utility may only reduce its purchases to zero for up to 90 days per contract year. The price carries a fuel floor and recovers excess fuel cost, so the customer, not Hallador, carries fuel risk for the life of the contract.

Brent BilslandChairman and CEO

The agreement took effect on signing and required no regulatory approval, and there are no margin calls. We conceded some economics to reduce our risk, and the contract is structured to protect our margins over a long period of time. All of these factors combined point to the value of Merom. The financing trouble that has made headlines in the AI industry recently involves the neoclouds, companies that buy computing hardware with borrowed money and rent it out with little revenue from anything else. The hyperscalers borrow too, but they borrow against investment-grade balance sheets and hundreds of billions of dollars of operating cash flow from businesses that have little to do with AI. We understand why the credit market is nervous about the neoclouds, but they are not our customers, and they are not our credit risk.

FULL TRANSCRIPT

Continue the full translated transcript in StockNow.

Log in to unlock every statement, the English original, and speaker-by-speaker history.

Log in for the full transcript

Other earnings calls that day

View calls from this day