Tamboran Resources 2026 Q4 Earnings Call
Review the key takeaways and the transcript of this earnings call.
- Tamboran Resources delivered first gas sales from the Beetaloo Basin to the Northern Territory gas market, with gas flowing for 20 days at the time of the call.
- Current volumes are limited by Northern Territory Government nominations of 25 terajoules per day as the territory exits its lower demand season.
- The SS-2 stimulation campaign completed 178 stages across 30,000 lateral feet, including a Beetaloo Basin record 12 stages completed in a day using a zipper frack approach.
- The Sturt Plateau Compression Facility was completed on time at approximately $9 million below the forecasted budget, although commissioning remains ongoing.
- Tamboran raised US$186 million net of fees through an underwritten public offer and institutional and retail entitlement during the quarter.
- At quarter-end, Tamboran had US$225 million in cash and US$31 million in undrawn debt for funding of the SPCF; including the expected US$15 million receipt from Daly Waters Energy, pro forma cash was US$240 million.
- Drilling of the first two wells in the three-well SS-1 campaign was completed, with the third well drilling ahead, while Santos commenced a two-well appraisal program on EP 161.
- The company reported improved drilling performance from an improved drill bit design, anti-vibration tools, rig modifications and directional planning through the Moroak Sandstone.
- Ten stages using locally supplied Beetaloo Red Sand were completed across various locations within the SS-2 5H well, with no impact to pump pressures or fracture initiation and tracer results in line with other stages.
STOCKNOW INSIGHTS
Continue with outlook and guidance.
Log in to unlock executive comments and Q&A highlights.
Log in for the full summaryStockNow uses AI to translate and summarize earnings calls. Accuracy and completeness are not guaranteed.
Transcript
Preview the first fifteen paragraphs, organized by speaker.
Greetings, and welcome to the Tamboran Resources fourth quarter fiscal year 2026 earnings call. At this time, all participants are in listen only mode. A question and answer session will follow the formal presentation. You may be placed into question queue at any time by pressing star one on your telephone keypad. We ask you please ask one question, one follow-up, then return to the queue. As a reminder, this conference is being recorded. If anyone should require operator assistance, please press star zero. It is now my pleasure to turn the call over to Todd Abbott, Chief Executive Officer.
Todd, please go ahead. Hello everyone, and welcome to Tamboran Resources financial year 2026 fourth quarter earnings presentation.
My name is Todd Abbott, and I am the Chief Executive Officer of Tamboran Resources. I am joined here today by Chief Financial Officer, Eric Dyer, and VP, Investor Relations and Corporate Development, Chris Morbey. I will start by reviewing delivery against the commitments we made 12 months ago, then cover production and commissioning as we build towards plateau rates and contracted supply. I will also discuss what our latest well results and operating improvements mean for performance and cost as we continue to de-risk our asset. I will then review our funding position and close with the next development milestones before we take your questions. Moving to slide 2, you can see our disclaimer which relates to forward-looking statements within the presentation. I encourage you to review those at your convenience. And slide 3. The last few months have been a pivotal period for Tamboran and the Beetaloo Basin, as we have delivered on a key commitment and provided the next step in de-risking the basin.
We have delivered first gas sales from the Beetaloo to the Northern Territory gas market. Homes and businesses in Darwin are now being powered by a local onshore resource. These gas sales also bring royalties to the Northern Territory Government and native title holders, alongside job opportunities for Territorians. Tamboran already employs a significant local workforce, which we expect to grow as activity increases over the coming years. Moving to slide 4. Gas has now been flowing into the market for 20 days. Volumes are currently limited by market demand, with the Northern Territory Government nominating 25 terajoules per day as the territory comes out of its lower demand season.
We expect demand, and therefore nominations, to keep growing through the Northern Territory's peak demand period. We are currently in the commissioning period of the gas sales agreement. Once the agreement moves into the supply period, take or pay provisions will apply to the 40 terajoule per day contract quantity, and we will be getting revenue based on that 40 terajoules per day. Any gas the offtaker does not take will be banked for future potential delivery. This gives us downside protection in the event of lower nominations during the contracted period. Regarding our flowback strategy, we will prioritize two wells to ensure that we are generating long-term production and well performance data to further de-risk the basin. The remaining wells will be managed as needed to recover flowback water and to close any gap to the allowable nominations.
In achieving this first gas milestone, our operations team have been working deliberately across multiple work streams. They successfully completed the stimulation campaign on the SS-2 pad in the Beetaloo Basin. The program utilized the Liberty Energy stimulation fleet that was imported into the basin in 2023. During the program, we completed 178 stages across 30,000 lateral feet. It was the largest stimulation campaign conducted in the basin. The zipper frack approach allowed us to achieve 20 hours of operations and a Beetaloo Basin record 12 stages completed in a day. This gives us and the market early evidence that we can execute completions more efficiently. The next measure of success is sustaining an improved pace across a full campaign, reducing downtime and bringing down completion cost per well.
We have also entered into a non-binding memorandum of understanding with Liberty Energy, setting out the intent to extend the hydraulic fracture stimulation of Marwin Services agreement, covering Tamboran's operations in the Beetaloo Basin. Liberty intends to begin phasing lower emissions pumping equipment into the Beetaloo fleet from 2027. Importantly, the campaign included 10 stages using the locally supplied Beetaloo Red Sand across various locations within the SS-2 5H well. The pumping and placement of the local sand was an identified risk going into the program. However, given we experienced no impact to pump pressures or fracture initiation during these stages, we are confident on our ability to place local sand in future campaigns.
Tracers across the horizontal length have shown that the stages are producing in line with all set wells, but these are still early days, and the true test will be the longer term flow rates and recoveries. We plan to further test our Beetaloo Red Sand during the upcoming stimulation program planned on the SS-1 pad. Success of that local sand is a key step in delivering near-term cost reduction for well completions. It is expected that sand could save $4 million per well with a 10,000-foot horizontal section compared to the sand imported from overseas. Those long-term flow rates and recoveries from those stages will help us assess how widely we can apply those savings. In conjunction with the upstream activity, the operations team successfully completed construction of the Sturt Plateau Compression Facility on time at approximately $9 million below the forecasted budget.
This allowed us to meet our commitment to the supply of the Northern Territory gas market during the quarter. The commissioning of the facility remains ongoing as we fine-tune control systems and refine equipment settings. During the commissioning period, we will be receiving 75% of the gas price. This is due to the interruptible nature of the supply. Once commissioning and production testing requirements are complete, we will commence delivery into the take-or-pay contract with the Northern Territory Government. During the quarter, the operations team also commenced drilling the three-well campaign on the SS-1 pad with the H&P FlexRig 3 rig. Drilling of the first two wells has been completed, with the third well currently drilling ahead. We continue to incorporate lessons from previous campaigns. This program includes first wells drilled with our improved drill bit design and anti-vibration tools. This resulted in record speeds through the Moroak formation.
Modifications to the rig have resulted in reduced mud temps, allowing increased average ROP in the lateral sections. We continue to work with our contract partners to improve efficiencies and reduce downtime, especially within the lateral section, and we believe these are addressable as we ramp up activity. In the East, drilling of the two-well appraisal program with Santos on EP 161 has also commenced with the Jibera South 1H and Newcastle South 1H wells in that depocenter. During the quarter, we significantly strengthened our balance sheet. In April, we raised US$186 million net of fees via an underwritten public offer and an institutional and retail entitlement. The funds from the raise solidify the balance sheet and provide us financial flexibility. At the end of the quarter, Tamboran had US$225 million in cash and US$31 million in undrawn debt for funding of the SPCF.
Including the US$15 million that we expect to receive from Daly Waters Energy, the pro forma cash position is US$240 million. Receipt of that US$15 million remains subject to certain conditions precedent. Over the next two quarters, we expect that under US GAAP, some revenue and costs related to the pilot project will be capitalized to the balance sheet during commissioning rather than flowing through the income statement. This is to avoid reporting volatility and means that the income statement will not reflect cash movements during the period. We expect to announce first quarterly gas sales and revenue in our 1Q fiscal 2027 earnings in November. The next phase of our development plan is to further delineate our gas resources across both depocenters in the Beetaloo Basin. This will be the focus of our 2027 and 2028 campaigns.
We are working with our joint venture partners, Daly Waters Energy and Impact in the West, and Santos in the East, to drill and stimulate at least six step-out wells over the next 18 months. We are progressing discussions with multiple parties to bring in a strategic partner. These strategic discussions and the upcoming appraisal work aim to align on resource delineation and commercialization pathways that will support a large-scale development and underpin new pipeline infrastructure. That infrastructure is expected to connect the Beetaloo Basin to multiple high-value markets. To close, we have delivered the first gas sales that we committed to 12 months ago and completed the compression facility on time and below the forecasted budget. Our latest drilling and stimulation work is showing where we can improve efficiency, while local sand offers a potential source of completion cost savings.
The equity raise has strengthened our balance sheet for the next phase of development. The priority now is to turn those achievements into sustained operating performance. That means completing commissioning and production testing, building towards plateau production and contracted supply, and demonstrating that the gains at well delivery can be repeated. Those are the measures I will use to judge our progress as we advance our development plans and partner discussions. As we close, I want to thank all Tamboran employees for their commitment, their performance, and their support for one another as we continue to grow, evolve, and deliver for our customers and shareholders.
Thank you. Thank you. We will now be conducting a question-and-answer session.
If you would like to be placed in the question queue, please press star one on your telephone keypad. A confirmation tone will indicate your line is in the question queue. If you would like to remove yourself from the queue, please press star two. We ask you please ask one question, one follow-up, then return to the queue. That is star one to be placed into question queue. Our first question today is coming from Scott Hanold from RBC Capital Markets. Your line is now live.
FULL TRANSCRIPT
Continue the full translated transcript in StockNow.
Log in to unlock every statement, the English original, and speaker-by-speaker history.
Log in for the full transcriptCall participants
9 people spoke on this call — only 1 are shown here.
PARTICIPANT LIST
View participant details in StockNow.
Log in to see executives and analysts, their roles, and complete speaking history.
Log in to view all participantsKeep exploring