Hut 8 2026 Q3 Earnings Call
Review the key takeaways and the transcript of this earnings call.
- Hut 8 reported 3rd quarter revenue of $71.1 million, compared with $83.5 million in the prior year period, while adjusted EBITDA increased to $33 million from $30.5 million.
- Net income was $189.5 million, of which $131.1 million was attributable to Hut 8, including a $413.8 million gain on digital assets.
- Compute revenue was $68.4 million versus $70 million in the prior year period; higher Bitcoin production from additional operating capacity at Vega and the re-energization of Drumheller largely offset lower average revenue per Bitcoin mined.
- AI cloud revenue increased as new customer contracts came online, partly offset by the sale of the traditional cloud business in August; Power revenue was $1.3 million versus $8.4 million, and digital infrastructure revenue was $1.4 million versus $5.1 million.
- As of September 30th, 2026, Hut 8 had approximately $156.9 million of cash, $3.6 billion of restricted cash and cash equivalents, and $2.8 billion of restricted short-term investments; Hut 8 also had about 1,361 unencumbered Bitcoin as of November 1st.
- The company reported approximately $7.6 billion of consolidated loans, notes payable, and other financial liabilities, of which approximately $7.5 billion related to Riverbend and Beacon Point project financings that are non-recourse to Hut 8's parent company.
- Hut 8 closed a $1.07 billion senior secured revolving credit facility in September, with no borrowings outstanding as of September 30th, 2026.
- Hut 8 repurchased approximately 3.3 million shares for approximately $250 million, funded with approximately 3,100 Bitcoin; its board authorized an increase in the share repurchase program from $250 million to $1 billion.
STOCKNOW INSIGHTS
Continue with outlook and guidance.
Log in to unlock executive comments and Q&A highlights.
Log in for the full summaryStockNow uses AI to translate and summarize earnings calls. Accuracy and completeness are not guaranteed.
Transcript
Preview the first fifteen paragraphs, organized by speaker.
Good morning, and welcome to Hut 8's third quarter 2026 financial results conference call. Joining us today are our CEO, Asher Genoot, and our CFO, Sean Glennan. Following the presentation, we will open the line for questions. This event is being recorded, and a transcript will be made available on our website. In addition to the press release issued earlier today, a full quarterly report on Form 10-Q is available at hut8.com, on our EDGAR profile at sec.gov, and on our SEDAR+ profile at sedarplus.ca. Unless otherwise indicated, all figures discussed today are in USD. Certain statements made during this call may constitute forward-looking statements within the meaning of applicable securities laws. These statements reflect current expectations and are subject to risks and uncertainties that could cause actual results to differ materially.
Certain key risks are detailed in our Form 10-K for the year ended December 31, 2025, and our other continuous disclosure documents. Except as required by law, we assume no obligation to update or revise any forward-looking statements. During the call, management may reference non-GAAP measures such as Adjusted EBITDA. We believe these metrics, alongside GAAP results, provide valuable insight into our performance. Reconciliations of GAAP and non-GAAP results are included in the tables accompanying today's press release, available on our website. I'll now turn the call over to Asher.
Thank you, Mark, and good morning, everyone. Over the past year, we have contracted 949 MW of IT capacity under long-term AI data center leases with or backed by investment-grade companies, representing approximately $27 billion of contracted revenue. Realizing that revenue and the returns that we underwrote against it requires three disciplines. First, the quality of the power and the contracts that we originate. Second, our execution in delivering what we have contracted. Third, our rigor in financing. Those are the three principles we outlined for investors in May. In my remarks this morning, we'll address each in turn, origination, delivery, and financing. Sean will then review the results in detail. Before I turn to the quarter, I want to step back to the premise behind all three measures, because it explains why we sequence them in that order.
AI is delivered as software, but it is produced by physical infrastructure, power, land, transmission, buildings, cooling, equipment, and the people who operate them. The next generation of compute will be constrained not only by chips, but also by that infrastructure. Of everything that infrastructure requires, power is a scarcest input. That is why we are a power-first company. The input that is hardest to secure is the one we secure first. We developed the discipline of building within that constraint in Bitcoin mining, which required us to operate power-dense compute to manage cooling and uptime, and to procure and build quickly. AI is the largest opportunity we have yet encountered to apply that same discipline. Securing power, however, only earns the right to build. Converting it into contracted revenue depends on how efficiently we build, and that is the second part of what defines Hut 8.
I am convinced that the infrastructure behind AI can be built better than it is being built today, faster, at a lower cost, and without compromising on quality. Many of today's data centers resemble NASA rocket programs, remarkable engineering, but complex, expensive, and slow to deliver. Frankly, this is the mold that River Bend and Beacon Point Phase 1 follow. This approach makes sense when the build-out is small, but it will not work at the multi-gigawatt scale at which I expect Hut 8 to build. Our future builds, therefore, start with a different question, what each system must do and how it should be designed and delivered. We are rethinking builds from there with the aim of improving speed and cost efficiency, with quality held as a constant, not the variable. We have done this before.
Vega, a Bitcoin mining facility we designed in-house with direct liquid-to-chip cooling, was built in under six months. We believe we can apply the same approach to our future builds, and we believe that our ability to rethink builds to be more cost-efficient and shorten delivery times while maintaining quality through innovation will differentiate Hut 8 with customers. With that as context, I will turn to the quarter, beginning with origination, which is where the power is secured. For investors, origination is a measure of whether we control sufficient power on terms that support attractive commercialization opportunities to continue converting our pipeline into leases comparable to those at River Bend and Beacon Point. We originate through three channels, and we advanced each throughout the quarter. The first is front-of-the-meter greenfield development. Our pipeline now includes more than 6.4 GW under diligence and under exclusivity.
Capacity under exclusivity, the stage at which we have secured a defined path to ownership, increased by approximately 1.3 GW during the quarter as existing projects advanced and new projects were originated. Pipeline alone does not answer the question investors ask most often about that pipeline, which is how geographically diversified is it? This quarter, we are providing a breakdown of our front-of-the-meter greenfield pipeline by geography. The largest shares are in MISO, PJM, and SERC. Less than 5% is in ERCOT. That distribution reduces our regulatory and price exposure in any single market. It does not, however, diminish the value of our existing Texas interconnects, which we believe have become more valuable as ERCOT's revised interconnection process has lengthened the time required to secure approvals for new interconnections.
The second channel is behind-the-meter development, which allows us to unlock power and accelerate delivery where traditional grid timelines are constrained, and which builds on years of experience developing and operating such projects. We are actively evaluating opportunities across our campuses. Consistent with our disciplined approach, however, we do not include that capacity in our reported development pipeline until a contract is executed. River Bend illustrates that point. Beyond the current phase under construction, we continue to develop the site. We have cleared 184 acres for campus expansion and are advancing site preparation now, so that construction can begin promptly once the next phase is commercialized and approvals are secured. The third channel is corporate development, in which we acquire powered assets.
Our approach here is the one that produced Beacon Point, where we secured the power, underwrote the site on Bitcoin mining as its initial use, and applied our greenfield development capabilities to advance the site and convert it into an AI data center campus. This quarter, corporate development yielded another opportunity as we entered into a definitive agreement to acquire from affiliates of Quoin two energized data center sites in West Texas, with up to 230 MW of utility capacity upon full energization, subject to final power approvals and infrastructure development. Second, delivery. Each lease we sign obligates us to deliver capacity by a contracted date, and the lease revenue begins only on delivery. For investors, delivery is therefore the measure of whether the capacity we have contracted begins generating rent on the dates to which we committed, and it is our central operating priority.
Construction at River Bend and Beacon Point Phase 1 remains on track to meet our delivery targets, and both projects are funded entirely at the project level. At River Bend, more than 1,200 people are on site. Structural steel, roof decking, and building foundations are complete on all four data halls. The slab at Data Hall 1 is also complete, and the remaining three data halls will follow through year-end. Roofing and precast wall panels have also been installed at Data Hall 1, with the remaining halls expected to follow through by mid-December, reducing the exposure of interior electrical and mechanical work to weather-related disruption. We expect to energize the substation in phases, and equipment installation has begun in Data Hall 1, starting with Vertiv IT power skids and SmartRun overhead modulars. At Beacon Point Phase 1, ground improvements are approximately 95% complete. Building foundation work and underground utilities installation are underway.
The steel erection is scheduled to begin this month. We have also begun foundation work for the substation. For Beacon Point Phase 2, civil design and surveying are underway. We also amended the Beacon Point Phase 2 lease with our customer, extending its term from 15 to 17 years. The extension serves both parties. For our customer, it secures capacity over a longer horizon, which reflects the durability of demand for power. For Hut 8, it adds two years of contracted revenue for lenders to underwrite, which should help offset potentially higher financing costs as we look to finance Phase 2. The amendment applies to Phase 2 only. Phase 1 remains on its existing terms, and the construction and financing framework for the campus is unchanged.
Delivery also depends on the support of the communities in which we build, which we treat as a precondition of development rather than as an obstacle to be managed. River Bend demonstrates what is required to convert power-first approach into a real project. Power, transmission, land, construction, partners, and community alignment must come together in the right order. That is what more than 300 investors, analysts, media, government stakeholders, and community members saw when they visited River Bend last month. I joined Governor Jeff Landry of Louisiana and leaders from Anthropic, Entergy Louisiana, Broadcom, Vertiv, and Jacobs to discuss the future of American AI infrastructure, and those discussions reached one conclusion: demand, supply, delivery, and policy are inseparable. Sound technical plans matter, but durable projects are built transparently in partnerships with the people who live and work nearby. In Louisiana, that partnership has taken specific form.
We are investing approximately $16 million in a new water well and nearly 8 miles of water infrastructure, none of which will be used to cool the data center, and which will be transferred to the parish at no cost to local taxpayers and can serve more than 4,000 households and 200 local employers. We also made a $10 million payment in lieu of taxes, bringing tax revenue to West Feliciana Parish one year earlier than it otherwise would have arrived, supporting local government, schools, and law enforcement, including $7,000 stipends for school employees in each of the next two school years and payments of up to $8,000 for eligible sheriff office personnel. At Beacon Point in Texas, the commitments differ in form, but not in principle.
We are funding the electrical upgrades that our campus requires so that those costs are not shifted to residential ratepayers, and the campus uses closed-loop cooling design to minimize local water demand. Across both phases, we anticipate approximately 1,900 construction jobs and more than 200 permanent positions, supported by partnerships with local educators and workforce organizations. We make these commitments because we believe a successful project must create lasting value, not only for our customers and shareholders, but also for the communities that host it. We uphold this philosophy by investing in the infrastructure, workforce, and partnerships that allow our projects and the communities around them to grow together. Third, financing. For investors, how we finance our projects is a measure of our ability to limit risk to the parent balance sheet and avoid dilution for existing shareholders.
Two of the main questions we've been asked this quarter get directly to that point. How are our current builds progressing, and might we need to issue additional equity to support them? The answers are straightforward. We remain on schedule, and we do not expect to issue additional equity to support River Bend or Beacon Point. River Bend and Beacon Point Phase 1 are funded through completion with investment-grade project bonds of $3.25 billion for River Bend and $4.25 billion for Beacon Point Phase 1, each non-recourse to Hut 8. We were able to raise investment-grade financing for both projects through a comprehensive approach to risk mitigation. Operating in Bitcoin mining taught us how quickly markets can change, and inflation and interest rate expansion are present realities. We cannot control the market, but we can control who we secure in advance and how we contract.
FULL TRANSCRIPT
Continue the full translated transcript in StockNow.
Log in to unlock every statement, the English original, and speaker-by-speaker history.
Log in for the full transcriptCall participants
17 people spoke on this call — only 2 are shown here.