WhiteFiber 2026 Q3 Earnings Call
Review the key takeaways and the transcript of this earnings call.
- White Fiber reported that all 40 megawatts of contracted IT capacity at NC1 are operational and billing under the contract; the contract value is approximately $865 million over 10 years.
- NC1 reached full billing later than expected after shipping disruptions related to the Middle East conflict, switchgear integration and commissioning issues, and a software issue; the second 20-megawatt hall began full billing on November 9th, and management does not expect late delivery penalties.
- NC1 development costs are expected to finish just below $9 million per gross megawatt, within the original budget range of $7 to $9 million, excluding site acquisition costs and net of customer-funded non-recurring costs.
- White Fiber completed the $60 million acquisition of NC2 and NC3 in Yadkin County; the sites are zoned for data center use and have at least 60 megawatts of initial gross utility capacity.
- The company reported approximately $750 million in new cloud services contract value across 5 customers since the prior earnings call, covering dedicated GPU services and managed services; new dedicated compute agreements average about 4.2 years and cover roughly 13,000 GPUs.
- Total signed dedicated compute contracts are about 20,000 GPUs, and the fully deployed signed cloud services portfolio is expected to generate about $365 million in annualized revenue.
- White Fiber signed 4 managed services agreements with a total contract value of about $58 million and expects about $15 million in annual recurring revenue once they are fully deployed.
- Third-quarter revenue was $24 million, up 19% from a year ago; colocation revenue more than tripled to $5.6 million, while cloud revenue was $18.1 million, including a $3.4 million customer termination fee.
- Excluding the termination fee, cloud revenue declined approximately 18% year over year as the company transitioned to new deployments scheduled to enter service over the coming quarters.
- Gross profit excluding depreciation and amortization was $13.7 million, a margin of approximately 57%, compared with 59% last quarter; G&A was $18 million, down 16% year over year, and adjusted EBITDA was approximately breakeven.
- Net loss was $101.4 million, including an $80.8 million induced conversion expense associated with the August repurchase of convertible notes.
- White Fiber ended September with $138.5 million of cash and cash equivalents and $9 million of restricted cash; deferred revenue, largely customer prepayments, was $306 million, up from $80 million at year-end.
- Remaining performance obligations were $729 million as of September 30th; future payments under colocation leases, excluded from that figure, totaled approximately $421 million at quarter end.
STOCKNOW INSIGHTS
Continue with outlook and guidance.
Log in to unlock executive comments and Q&A highlights.
Log in for the full summaryStockNow uses AI to translate and summarize earnings calls. Accuracy and completeness are not guaranteed.
Transcript
Preview the first fifteen paragraphs, organized by speaker.
Hello, and welcome to the White Fiber Third Quarter 2026 Earnings Conference Call. Good afternoon, and thank you for joining us. We will begin with prepared remarks from management, followed by a question-and-answer session. During the Q&A, if you would like to ask a question, please press star one on your telephone keypad. As a reminder, today's conference is being recorded. I would now like to turn the call over to your host, Cameron Schnier, Senior Vice President of Capital Markets and Corporate Strategy at White Fiber.
Cameron, please go ahead. Thank you, and welcome to the White Fiber Third Quarter 2026 Earnings Call.
Joining me today are Sam Tabar, our Chief Executive Officer, and Justin Zhu, our Chief Financial Officer. Before we begin, I'd like to remind everyone that some of the statements we make on this call are forward-looking in nature and subject to risks and uncertainties that could cause actual results to differ materially. Such risks and uncertainties include, but are not limited to, those factors described in today's earnings press release, our Form 10-Q for the quarter ended September 30, 2026, filed today, as well as other filings we make with the SEC from time to time. Our remarks today may also include non-GAAP financial measures. Reconciliations to the most directly comparable GAAP measures can be found in our Form 10-Q and in the earnings press release posted on our website.
Following our prepared remarks, we'll open the call for questions. With that, I'll turn the call over to Sam to discuss our performance.
Sam? Thank you, Cam, and thank you, everyone, for joining us.
We've reached two important milestones at NC-1. First, all 40 MW of contracted IT capacity are now operational, and we have begun billing for the overall contracted capacity. As a reminder, the contract value is approximately $865 million over 10 years. Second, we've signed a $300 million secured credit facility for the project. Third, since our last earnings call, we've also signed more than $700 million in new cloud services contract value. That includes our first capital-light managed services agreements. At the same time, demand for our next North Carolina sites, NC-2 and NC-3, continues to materially strengthen. Together, these developments give us a stronger foundation for growth in 2027. Our focus now is execution, bringing signed contracts into service, securing the funding to support them, and choosing our next investments carefully. Let me start with NC-1.
Completing this project is a significant milestone. It shows that our retrofit model can deliver complex AI infrastructure at scale. Despite the challenges, we brought 40 MW of IT capacity into service in less than 11 months. Getting to full billing took longer than we expected. I want to explain why. Shipping disruptions related to the Middle East conflict delayed our original switchgear. To keep the project moving, we sourced replacement equipment and adapted the electrical design. Our team then had to resolve integration and commissioning issues with that equipment. Billing for the first 20 MW hall began in mid-August. A switchgear software issue later interrupted service and billing. Both resumed on September 23rd. Further switchgear commissioning issues delayed the second hall, including the final 5 MW. As a result, we reached full contracted billing later than we expected in August.
The issue affecting that final capacity has now been resolved. Full billing for the second 20 MW hall has begun on November 9th. All 40 MW are now billing under the contract. Importantly, we do not expect late delivery penalties related to these issues. We expect development costs to finish just below $9 million per gross megawatt. That is within our original budget range of $7 million-$9 million. That figure excludes the site acquisition costs and is net of customer-funded non-recurring costs. NC-1 gives us an established U.S. operating base and a development model we can build off. We're applying what we learned to procurement, testing, and commissioning to NC-2 and NC-3. We recently completed the $60 million acquisition of these two sites in Yadkin County. We believe they are exceptionally well-suited to our retrofit strategy.
They have existing industrial buildings, an on-site substation, and valuable electrical infrastructure. We expect at least 60 MW of initial gross utility capacity. They're also about 55 miles away from NC-1. That means we could draw on our existing workforce and regional resources to support development and operations. These sites show why we favor retrofits. Existing buildings and electrical infrastructure gives us a head start. They can shorten delivery timelines and reduce construction and permitting risk compared with building from the ground up. Finding sites with these advantages is one of our strengths. The customer interest we're seeing supports our confidence in the acquisition. We see an opportunity to turn this infrastructure into assets that generate cash for many years. We're targeting initial capacity in late 2027. Both NC-2 and NC-3 are already zoned for data center use, which removes an important hurdle.
Delivery will still depend on power availability, customer commitments, financing, and the remaining approvals. We're also applying our community engagement experience in Madison. Strong local relationships are an important part of how we develop these projects. Across North Carolina, we're in advanced customer discussions for about 105 MW of gross capacity delivered for 2027. That includes about 45 MW of expansion at NC-1 and 60 MW across NC-2 and 3. Interest in NC-2 and 3 is substantially stronger than the interest we saw a year ago when we were marketing the first phase of NC-1. We have a broad range of interested customers, more non-binding letters of intent, and stronger prospective counterparties. Some of these proposals come directly from investment-grade counterparties. Others include investment-grade credit support. That gives us more choice in selecting agreements we can finance and deliver successfully. Demand is also expanding beyond AI infrastructure providers.
We're seeing direct interest from Fortune 100 companies for deployments below 50 MW, as well as smaller purpose-built projects. Market sentiment has been weak, but the customer demand we see continues to grow. More enterprises want dedicated infrastructure for their own AI programs. We're also seeing opportunities tied to government-related demand. Over time, we expect enterprises and public sector customers to become a larger part of the market. They want dedicated compute, control over sensitive data, and infrastructure located in specific jurisdictions. Our colocation, cloud, and managed service business gives us several ways to meet those needs. Our experience at NC-1 has also sharpened our approach to these new projects. We require investment-grade credit at the project level, either directly from the customer or through a full credit wrap. We're structuring customer agreements and financing together from the outset.
We intend to move quickly toward delivery in 2027, but we will maintain those standards even if that affects the delivery date. As power becomes harder to secure, it matters more whether a site has potential capacity or power that can actually serve a customer. We believe existing electrical infrastructure combined with a credible delivery schedule will become increasingly valuable. Development costs have risen over the past year. Based on our current budgets, however, the pricing and terms in customer proposals would more than offset those increases. That creates an opportunity to earn higher yields on development costs than we achieved at NC-1. We also consider financing costs and terms. Ultimately, the return on the capital we commit will guide the agreements that we sign. Looking further ahead, we're preparing to deliver substantially more infrastructure in 2028 and beyond.
We're advancing sites and power, strengthening our teams and systems, and developing financing options. We want to be ready for the right opportunities while keeping flexibility when and how much capital we invest. Turning to Canada, MTL2 will host the Prime Intellect deployment we announced last quarter. The agreement covers 576 Vera Rubin GPUs over the initial three-year term. This will be our first deployment combining our own data center with our cloud services. The budget to complete the facility is about $25 million. Development debt is available through our Royal Bank of Canada facility. We're targeting facility readiness in early 2027, ahead of the start of GPU services in the second quarter. Bringing facility design and GPU deployment together gives us more control over delivery and operations. Most of our near-term new data center capacity will continue to serve pure colocation customers.
We'll combine our facilities and cloud services selectively where the economics make sense. Owning facilities also gives us more options when GPU contracts expire. Where we have available capacity, we can redeploy equipment to extend its revenue-generating life. We can also serve shorter-term demand when pricing is attractive. At MTL2, we're evaluating behind-the-meter power options that could bring additional capacity online sooner. We're also continuing to pursue utility expansion across our Montreal portfolio. Turning to cloud services. We continue to convert demand into larger multi-year agreements. Since our last earnings call, we've signed approximately $750 million in new contract value across five customers. These contracts cover dedicated GPU services and managed services. They include IG counterparties, new customers, and larger commitments from existing customers. They also establish our cloud presence in Sydney and Dublin. In both cases, customer demand is driving our expansion.
The new dedicated compute agreements have an average term of about 4.2 years and cover roughly 13,000 GPUs. That brings our total signed dedicated compute contracts to about 20,000 GPUs. The new deployments are scheduled to enter service between late in the fourth quarter and the second quarter of 2027. Once our signed cloud services portfolio is fully deployed, we expect it to generate about $365 million in annualized revenue. We are targeting that run rate by mid-2027. The timing depends on equipment and data center readiness, customer acceptance, and financing. Based on our current schedule, we expect fourth quarter cloud revenue to be roughly in line with the third quarter's $18.1 million. Growth in ongoing services should offset the one-time termination fee recognized in the third quarter. We then expect significant sequential growth in both the first and second quarters of 2027 as contracted deployments enter service.
FULL TRANSCRIPT
Continue the full translated transcript in StockNow.
Log in to unlock every statement, the English original, and speaker-by-speaker history.
Log in for the full transcriptCall participants
15 people spoke on this call — only 2 are shown here.
PARTICIPANT LIST
View participant details in StockNow.
Log in to see executives and analysts, their roles, and complete speaking history.
Log in to view all participantsKeep exploring