Fervo Energy Company 2026 Q3 Earnings Call

Review the key takeaways and the transcript of this earnings call.

PeriodQ3 2026Duration1 hr 2 minParticipants14

Transcript

Preview the first fifteen paragraphs, organized by speaker.

Operator

And welcome to Fervo's third quarter 2026 earnings conference call. At this time, all participants are in a listen-only mode. A brief question and answer session will follow the prepared remarks. As a reminder, this conference is being recorded. It is now my pleasure to introduce your host, Paxton Bentzinger, Senior Director of Corporate Development and Investor Relations. Please go ahead, sir. Thank you.

Paxton BentzingerSenior Director of Corporate Development and Investor Relations

Good morning, everyone, and welcome to Fervo Energy's Q3 2026 earnings call. Joining us today are Tim Latimer, co-founder and Chief Executive Officer, and David Ulrey, Chief Financial Officer. Before we begin, I'd like to remind everyone that today's discussion will contain forward-looking statements within the meaning of applicable securities laws. These statements reflect management's current expectations and assumptions and involve known and unknown risks and uncertainties that could cause actual results to differ materially. Please refer to the forward-looking statements and risk factors disclosed in today's earnings release and in our filings with the SEC. Additionally, today's discussion may include certain non-GAAP financial measures. Reconciliation tables are provided in the appendix of the earnings release as applicable. Now over to Tim to kick things off.

Tim LatimerCo-Founder and CEO

Thank you, Paxton, and good morning, everyone. I'll start with the most important development of the quarter. Our first GeoBlock at Cape Station is in commercial operation, delivering power to the grid and generating revenue under our power purchase agreement. A few years ago, enhanced geothermal was an idea recently proven with a pilot that had just begun operating. Today, it is a 33 MW power plant consistently delivering clean, firm electricity. When we last spoke in August, I said we'd judge our progress on four things. First, the strength of our pipeline. Second, how well and how quickly our modular approach serves customers. Third, our license to operate in the communities where we build. And fourth, our execution in the field. This quarter, we advanced on all four, and Cape Station is the clearest evidence.

Tim LatimerCo-Founder and CEO

Cape Station's first GeoBlock is the first greenfield enhanced geothermal system development in the world to reach commercial operation, and it was built in just 23 months. It demonstrates that enhanced geothermal can deliver reliable, carbon-free power at utility scale. We firmly believe that integrating modularity and best-in-class continuous improvement into infrastructure construction will drive tighter delivery timelines, and we're proud to have taken the first step in delivering this promise by completing our first GeoBlock ahead of schedule. During this call, I'll elaborate on the startup of operations before turning to our recent PPA with Google, which we believe is the largest enhanced geothermal PPA signed to date. I'll also speak about continued operational success at Cape Station, policy tailwinds, and progress across our pipeline. Before we go further, I want to talk about safety. Nothing we build matters if we don't build it the right way.

Tim LatimerCo-Founder and CEO

Our trailing 12-month total recordable incident rate now stands at 0.10, even as we scale up construction and operations at Cape Station. This quarter, our facilities construction crew also reached a major milestone, 1 million hours worked without a recordable incident. The men and women building our GeoBlocks do complex, demanding work, including work at heights, hot work, and exposure to the elements, so that reliable clean energy can be built in America. We are deeply grateful for their efforts. 1 million hours without a recordable incident reflects the seriousness with which we approach this work and the tools and processes that let it be done safely. At Fervo, we have said that we want to show that you can be at the forefront of innovation and still lead in health, safety, and the environment. This milestone is strong evidence that innovation and safety can go hand in hand.

Tim LatimerCo-Founder and CEO

Now, back to Cape Station. On September 30th, we declared commercial operation at our first GeoBlock, ahead of our contractual deadline. We synchronized to the grid on September 24th, and today, GeoBlock 1 is generating revenue under its PPA. In just 23 months, we turned an empty plot of land into a fully operational power unit. This milestone sends a clear message to customers, utilities, regulators, and other developers. Enhanced geothermal is now delivering at utility scale. We took science and intellectual property validated at Project Red and built a 33 MW full-scale GeoBlock that is delivering on our PPA, supported by project finance, and we delivered it on time. We are still early in our overall Cape Phase 1 operational life cycle, but while our pilot proved the building blocks of EGS, Cape Phase 1 data is beginning to confirm the benefits of operating EGS at scale.

Tim LatimerCo-Founder and CEO

GeoBlock 1 is performing in line with our operational expectations, including both production performance and power delivered under our PPA. Said simply, brine is arriving at the power plant at the designed volume and temperature, and electricity is being sold to the plant. GeoBlock 1 has given us the playbook. It has taught us about commissioning sequence, equipment and controls, contractor coordination, and regulatory approvals. We have run that playbook once, and now we run it repeatedly, improving each time we do. GeoBlocks 2 and 3 are on track with the timeline we laid out during our IPO. Both have reached mechanical completion. GeoBlock 2 has achieved grid sync, a major milestone which marks the end of hot commissioning. The plant is now in its tuning and early operations phase, exporting test energy to the grid.

Tim LatimerCo-Founder and CEO

GeoBlock 3 is close behind in cold commissioning, where we are testing the mechanical and electrical systems prior to introducing brine. We continue to expect commercial operation for these GeoBlocks by January 1st, 2027, which puts us on track to deliver approximately 100 MW of firm, clean power from Fervo's first three GeoBlocks by 2027. As we deploy our repeatable GeoBlock delivery model across other GeoClusters, both in Utah and in other states, we expect efficiencies to compound in terms of both speed and cost. Over time, we are confident we can build and commission GeoBlocks in fewer than 18 months. This brings me to what we are now calling Cape Google 400. GeoBlocks 4 through 11, the next eight units from our factory model that we will deliver to Google in 2028 under our recently signed PPA. These GeoBlocks are on track for mid-2028 delivery.

Tim LatimerCo-Founder and CEO

Let me turn now to the details of that agreement. In September, we announced what we believe is the largest enhanced geothermal power purchase agreement signed to date. It is a 15-year take-or-pay agreement, meaning Google is committed to paying for this power irrespective of the Beaver County data center plans, on terms that are fixed for the life of the contract. The agreement covers approximately 396 MW, delivered in four tranches of 99 MW each, with commercial operation targeted again in mid-2028, and the full set of GeoBlocks targeted to be online before the end of 2028. Construction is already underway, and I will share that progress shortly. Beyond the 396 MW contracted, we also committed to offer Google an expansion option of approximately 600 MW, which would bring the total to 1 GW.

Tim LatimerCo-Founder and CEO

Let me explain how delivery works under this agreement, because the structure is as important as the size. The signed 396 MW is the first layer, and it is initially grid connected. For Fervo, it is a firm, binding, and financeable contract that we can build against today, with parent guarantees from both Fervo and Alphabet behind it. For Google, we believe grid connectivity means the power they are buying has value regardless of how much of the power they consume, as Google can monetize power in the broader market. That is the point of this structure. It lowers project-on-project risk. We build Cape Station on our schedule, Google can develop a potential data center on their schedule, and neither party is waiting on the other. The second layer, the 600 MW expansion option, is behind the meter.

Tim LatimerCo-Founder and CEO

Unlike the 396 MW, which are grid connected, Fervo and Google are pursuing direct-to-load delivery for this expansion to the potential regional data center. This would be under Utah's SB132, a framework that lets large load customers connect directly to new generation, with protections for existing ratepayers. Our joint work to seek regulatory approval is underway, and we will share updates as this progresses. We are working on all of this with the same commitment to transparency and high-quality stakeholder engagement as we conduct with the rest of our business. Our partnership with Google adheres to the Geothermal Sustainable Development Pact, the voluntary standards I spoke about last quarter. In October, we were at Google's community event in Milford High School, where 250 neighbors came to learn about the potential data center and ask questions.

Tim LatimerCo-Founder and CEO

We are pleased with our progress to date, proud to partner with Google, and honored to operate in a community of engaged, invested citizens. Of course, everything we do comes back to execution in the field, so I will turn to construction. Work on Cape Google 400 continues on track across all eight 50 MW GeoBlocks, our standard design going forward. As I mentioned, we expect first power from these GeoBlocks in mid-2028, ramping to approximately 400 MW by the end of that year. Since last quarter's call, the first set of 50 MW turbines has passed factory acceptance tests, and we have accepted delivery of major equipment in line with our development plan, including recuperators and over 60% of all air-cooled condensers. On the subsurface side, we now have four H&P FlexRig3 rigs running at Cape Station. Drilling for GeoBlocks 4 through 11 is approximately 18% complete.

Tim LatimerCo-Founder and CEO

Our drilling results continue to improve as we drill more wells with our 3.0 design. Recall that our 3.0 design includes extending laterals to 7,500 feet, stepping up the lateral diameter to 8 and 5/8 inch casing, and targeting an average reservoir temperature of 430 degrees Fahrenheit. Each of these changes results in more power capacity through higher flow rates and higher temperatures. Reducing costs and increasing production are not the result of any single breakthrough. They are the result of intentional iterative improvement, where small changes compound into large increases in productivity. Dissolvable plugs and a redesigned toe prep reduce completion time and complexity. Rotary steerable systems and insulated drill pipe allow us to reach deeper, hotter rock without slowing down.

Tim LatimerCo-Founder and CEO

Procurement at scale is driving cost efficiencies on our surface equipment, where our ORC framework with Mitsubishi Heavy Industries, through its Turboden subsidiary, provides better pricing and firm delivery timelines on the equipment at the heart of each GeoBlock. No single action will win the day on cost reduction, but what Fervo is demonstrating is that through our methodical approach to development and our dedication to continuous improvement, we continue to remove cost from the system. As a result, we are positioned to achieve $5,500 per kilowatt of installed CapEx for GeoBlocks 4 through 11. Our long-term target remains at $3,000 per kilowatt. We maintain a keen focus on returns-oriented deployment of capital, where each dollar spent must justify its economic value.

Tim LatimerCo-Founder and CEO

Last quarter, we spoke about using small amounts of capital toward this effort, and one area we have identified is that by pairing relatively small amounts of solar with our GeoBlocks to power our station auxiliary load, we increase the amount of high-value geothermal power that is available for sale under our PPAs. We expect to continue identifying opportunities like these, where through our repeatable approach, we drive costs down and improve returns. Next, I would like to cover policy updates. We continue to see bipartisan support for geothermal at the federal level, support that has been notably broad and durable across administrations. The Department of the Interior recently directed the Bureau of Land Management to allow certain early exploration activities with expedited approval. When we announced our 396 MW power purchase agreement with Google, Interior Secretary Burgum congratulated Google and Fervo.

FULL TRANSCRIPT

Continue the full translated transcript in StockNow.

Log in to unlock every statement, the English original, and speaker-by-speaker history.

Log in for the full transcript