Big Sky Industrial 2026 Q3 Earnings Call
Review the key takeaways and the transcript of this earnings call.
- Big Sky Industrial Inc. reported 3rd quarter 2026 revenue of $2 million, up 12% from $1.7 million a year ago, as a 30% increase in average realized price to $63.83 per BOE more than offset lower volumes following the 2025 divestiture.
- Production was 30,628 BOE, 76% oil; lease operating expense was $2.1 million, including approximately $1.2 million of remediation and related costs from a produced-fluid release in legacy oil operations.
- Excluding remediation costs, lease operating expense was $0.9 million, or $29.71 per BOE, essentially flat with $29.58 a year ago; adjusted EBITDA was negative $0.8 million versus negative $1.3 million a year ago, and net loss was $3.5 million, or $0.07 per share.
- Cash general and administrative expense was $1.6 million, compared with $1.7 million a year ago and $1.8 million in the second quarter.
- The company ended the quarter with $2.9 million of cash and $14.4 million of total liquidity, including $11.5 million of undrawn capacity under its senior secured credit facility, which has a $20 million borrowing base, no financial covenant testing through the quarter ending March 31st, 2027, and a May 2029 maturity.
- Phase 1 infill gathering and injection lines are complete, production wells are drilled and completed, Class 2 injection wells are operational, long-lead equipment including company-owned power generation has been procured, and processing-facility fabrication is underway.
- Big Sky Industrial Inc.'s helium is covered by a 5-year, 100% take-or-pay contract for 1.2 million cubic feet a month at a fixed plant gate price of $285 per MCF, with CPI escalation beginning March 1st, 2028, and a pricing redetermination in year 3; the buyer handles transportation, logistics, and delivery.
- The Department of Energy designated helium a critical material under the Energy Act of 2020 on October 23rd, citing its role in semiconductor manufacturing and growing supply chain risk.
STOCKNOW INSIGHTS
Continue with outlook and guidance.
Log in to unlock executive comments and Q&A highlights.
Log in for the full summaryStockNow uses AI to translate and summarize earnings calls. Accuracy and completeness are not guaranteed.
Transcript
Preview the first fifteen paragraphs, organized by speaker.
Greetings, and welcome to the Big Sky Industrial Inc.'s third quarter 2026 earnings call. I will now turn the conference over to Mason McGuire, VP of Finance and Strategy.
Good morning, and welcome to Big Sky Industrial Inc. third quarter 2026 earnings conference call. All participants are in listen-only mode. Following management's prepared remarks, there will be a question-and-answer session for analysts. Today's call is being recorded, and a replay will be available on the investor relations section of the company's website at bigskyindustrialinc.com. Before we begin, I would like to remind everyone that today's discussion will include forward-looking statements within the meaning of the federal securities laws. These statements are based on management's current expectations and are subject to risks and uncertainties that could cause actual results to materially differ. Please refer to the company's most recent SEC filings, including the Form 10-Q filed yesterday and the Form 10-K, for a discussion of these risks. Statements made on this call speak only as of today, and the company undertakes no obligation to update them.
Joining us this morning are Ryan Smith, President and Chief Executive Officer, and Mark Zajac, Chief Financial Officer. I'll now turn the call over to Mr. Smith.
Thanks, Mason, and good morning, everyone. The third quarter was about execution. When we spoke in August, I said every structural piece of phase 1 was in place, engineering, permitting, EPC, funding, and offtake, and that what was left between here and first revenue was execution. That is where this team has spent the last 90 days in Houston and in Montana, and we're pleased with where the project stands. The field side of phase 1 is now built. Our in-field gathering and injection lines are complete. Our long lead equipment has been procured, including the power generation that will power the plant. Fabrication of the processing facility is underway, and construction remains on schedule. We're targeting first production in spring 2027, and our helium is sold from day one. Here's how I'll walk through the call this morning.
Construction and operations first, then a direct update on our MRV application, then our commercial position and the market we're selling into. Mark Zajac will take you through the quarter and the capital structure, and I'll come back at the end with what's ahead. I'm going to start in the field because that's where the progress this quarter is most visible. Our in-field gathering and injection lines are complete. Those are the lines that bring gas from our production wells to the processing facility and carry CO2 from the plant to the Big Rose sequestration asset. The production wells are drilled, completed, and ready to tie in, and our Class II injection wells are operational. In other words, the field side of Phase 1, gas in, helium purified and sold, and CO2 captured is in place and ready for the plant.
On the plant, our long lead equipment has been procured, including company-owned power generation. In August, we identified the generators as the longest lead time item on the project. They are purchased, on site, and owning our generation puts plant uptime in our own hands from day one, while significantly improving our operational costs going forward. Fabrication of the modular processing facility is underway with our EPC partner. The modular design is a big reason we remain comfortable and on schedule. Most of the build happens in a controlled fabrication environment rather than in the field, and far less can go sideways on site. On-site civil work begins in the coming weeks, and equipment installation runs from late in the fourth quarter into the first quarter of next year. We're targeting first production in spring 2027, and I want to be clear why we framed it as a window.
It leaves sensible room for commissioning and for a Montana winter, and I'd rather give a window than a specific date. At initial operations, the plant is designed to produce greater than 14 million cubic feet of high-purity helium and to capture approximately 125,000 metric tons of CO2 a year. Now to the MRV, as I know it's on the front of the mind of many of you who've dialed in today. Our Big Rose MRV is in the final stage of the EPA's approval process. Big Rose is where we will sequester the CO2 captured in Phase 1 and in future phases. We submitted the plan on October 9, 2025, and because of the federal government shutdown, the agency accepted it on November 12, 2025. We have addressed the EPA's comments and are awaiting final agency action, and nothing in the agency's feedback has changed our expectation of approval.
While the process has taken longer than we optimistically hoped, historically, EPA approvals of comparable plants have generally taken 12 months or longer, so our timing is in line with precedent, even if we had hoped for a quicker outcome. The review is detailed by design. It covers how CO2 will be monitored, measured, and accounted for, including leak detection and verification of long-term sequestration, and the timing of the final decision rests with the agency. Our responsibility to this point has been to respond promptly and keep the project moving forward, and that's exactly what we have done. The MRV approval is not a condition to starting Phase 1 plant or to selling helium. Our injection wells are permitted, operational, so we can sequester CO2 from the first day the plant runs.
The approval timing does not change our resource base, our plant sequestration capacity, or our helium offtake terms. Its impact is when we start generating and monetizing 45Q credits, not on the underlying economics of the project. We're advancing our credit monetization work in parallel with the EPA review so that we're positioned to move forward once approval is received. Our second plan for Cut Bank was submitted on December 17, 2025. It supports CO2 enhanced oil recovery at our Cut Bank oil field over the longer term as we move through future phases, and it continues to move positively through the EPA process. Now to the commercial side of the platform. Our helium is sold from day one. The offtake we signed in April is a five-year, 100% take-or-pay contract with an investment-grade global industrial gas company.
1.2 million cubic feet a month at a fixed plant gate price of $285 per MCF, with CPI escalation beginning March 1, 2028, and a pricing redetermination in year three. The buyer handles all transportation, logistics, and delivery, so we realize the full $285 with no deductions. Volume risk and demand risk sit with an investment-grade counterparty, not with us. The market we're selling into continues to make our case for us. on October 23, the Department of Energy designated helium a critical material under the Energy Act of 2020, citing its essential role in semiconductor manufacturing and growing supply chain risk. We have said for some time that an American producer of a strategically important industrial gas matters a great deal right now, and that designation puts it in writing. There is no substitute for helium in semiconductors, medical imaging, fiber optics, or aerospace.
Domestic supply remains thin, and our Tier 3 redetermination gives us a way to participate in a stronger market. Cut Bank Oil Field keeps doing its job by providing low-decline oil production that supports the platform while we build, and the captive CO2 outlet for enhanced oil recovery in future phases. With that, let me hand it to Mark to walk through the third quarter results and the capital structure.
Thanks, Ryan, and good morning, everyone. I'll cover three things this morning: the quarter's results, including the remediation item and lease operating expense, our liquidity, and the financing work Ryan referenced. The full detail is in yesterday's press release and in our 10-Q. Starting with the quarter, revenue was $2 million, up 12% from $1.7 million a year ago, as a 30% increase in our average realized price to $63.83 per BOE, more than offset lower volumes following our 2025 divestiture. Production was 30,628 BOE, 76% oil. Lease operating expense was $2.1 million compared to $1 million a year ago. The increase reflects approximately $1.2 million of remediation and related costs from the previously disclosed release of produced fluids from a gathering line in our legacy oil operations, which was identified and remediated during the quarter.
We submitted a claim under our general liability policy, which provides $1 million of coverage for pollution cleanup costs after a $100,000 deductible, and we expect to recover up to $1 million of these costs. Because the claim is pending approval, no receivable has been recorded at the quarter end. Excluding these costs, lease operating expense was $0.9 million, or $29.71 per BOE, essentially flat with the $29.58 a year ago. Cash general administrative expense was $1.6 million, down from $1.7 million a year ago and $1.8 million in the second quarter, primarily on lower accounting and tax professional fees. Adjusted EBITDA, which excludes the $1.2 million of remediation costs, was negative $0.8 million compared to a negative $1.3 million a year ago. Net loss was $3.5 million, or seven cents per share.
On liquidity, we ended the quarter with $2.9 million of cash and $14.4 million of total liquidity, including $11.5 million of undrawn capacity under our senior secured credit facility. That facility carries a $20 million borrowing base, no financial covenant testing through the quarter ending March 31, 2027, and a May 20, 2029 maturity. On financing, we are running two complementary processes. The first is a new, larger senior secured credit facility. Our existing facility was sized for the start of the construction. As we approach first production with contracted helium revenue, we believe the asset supports more borrowing capacity, and a larger facility would expand that capacity and our financial flexibility. Those discussions are underway. The second is monetization of the Phase 1 Section 45Q credits.
Under tax law, 45Q credits are transferable, which makes the Phase 1 credit stream a financeable asset in its own right and a potential source of non-dilutive capital. Those discussions are progressing, and we will update the market as each process advances. With that, back to you, Ryan.
FULL TRANSCRIPT
Continue the full translated transcript in StockNow.
Log in to unlock every statement, the English original, and speaker-by-speaker history.
Log in for the full transcriptCall participants
6 people spoke on this call — only 2 are shown here.
PARTICIPANT LIST
View participant details in StockNow.
Log in to see executives and analysts, their roles, and complete speaking history.
Log in to view all participantsKeep exploring