Good morning, and welcome to the NextDecade Corporation's third quarter 2026 investor call and webcast. At this time, all participants are on a listen-only mode. A question-and-answer session will follow management's prepared remarks. If you'd like to enter the queue, the command is star one on your telephone keypad. If anyone should require operator assistance during the conference, please press star zero on your telephone keypad. As a reminder, this conference is being recorded. Now I'd like to turn the call over to your host, Megan Light, NextDecade's Vice President of Investor Relations. Thank you. You may begin.

Megan LightVP of Investor Relations

Thank you, and good morning, everyone. Welcome to NextDecade's third quarter 2026 investor update call and webcast. The slide presentation and access to the webcast for today's call are available on our website at www.next-decade.com. Today, I am joined by Matt Schatzman, NextDecade's Chairman and Chief Executive Officer, and John Zuklic, NextDecade's Chief Financial Officer. Before we begin, I would like to remind listeners that discussion on this call, including answers to your questions, contains forward-looking statements within the meaning of U.S. federal securities laws. These statements have been based on assumptions and analysis made by NextDecade in light of current expectations, perceptions of historical trends, current conditions, and projections about future events and trends. Although NextDecade believes that the expectations reflected in these forward-looking statements are reasonable, it can give no assurance that the expectations will prove to be correct.

Megan LightVP of Investor Relations

NextDecade's actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in NextDecade's periodic reports that are filed with and available from the Securities and Exchange Commission. In addition, discussion on this call includes references to certain non-GAAP financial measures, such as distributable cash flow. A definition of and additional information regarding these measures can be found in the appendix to our presentation. Now, I will turn the call over to Matt Schatzman, NextDecade's Chairman and Chief Executive Officer.

Matt SchatzmanChairman and CEO

Thank you and good morning. We continue to make excellent progress toward first LNG production at Rio Grande LNG. Phase 1 construction remains safe, on budget, and ahead of schedule. We remain on schedule to introduce hydrocarbons into the facility before year-end. Today, we are narrowing our guidance for first LNG production from train 1 to the second quarter of 2027, consistent with the early volume guidance we provided earlier this year and are reaffirming today. Train 1's guaranteed substantial completion date is near the end of the fourth quarter of 2027. We expect Bechtel to achieve substantial completion in the third quarter of 2027, which is one quarter early. Trains 2 and 3 also remain ahead of schedule and aligned with our early volume guidance. During the quarter, the main cryogenic heat exchanger was installed for train 2, and the first compressor string was set for train 3.

Matt SchatzmanChairman and CEO

We expect both trains to achieve substantial completion about one quarter ahead of their guaranteed schedules, consistent with Train 1. As outlined in our early volume and cash flow guidance, commissioning and early uncontracted volumes from RGLNG Trains 1 through 5 provide valuable market exposure to NextDecade over the next few years, and the current LNG market dynamics are very favorable. Spot LNG prices remain strong and have increased materially over the last year due to the loss of supply from the Middle East.

Matt SchatzmanChairman and CEO

Based on current forward LNG and U.S. gas prices, we estimate that volume-weighted average implied margins on the projected uncontracted volumes from Train 1 startup in 2027 through the DFCD under the Train 5 long-term SPAs at RGLNG, together with the impact of the 175 TBtu's we sold forward in Q1 of this year, to average over $6 per MMBtu, more than $1 per MMBtu above our base case guidance. Using these estimated implied margins for our projected uncontracted volumes, NextDecade's share of Rio Grande LNG project-level distributable cash flow during this period would total over $2.4 billion, or over 20% above the projected $2 billion of cash flow in our base case guidance.

Matt SchatzmanChairman and CEO

Each $1 per MMBtu change in the estimated volume weighted average implied margin on our uncontracted volumes from Train 1 startup through Train 5 DFCD, including the impact of the additional 175 TBtu's sold in Q1, would change NextDecade's projected share of project-level distributable cash flow by approximately $350 million-$400 million over the forecast period. As of September 2026, Trains 1 and 2 were nearly 80% complete. Engineering and procurement were nearly finished, construction was almost 70% complete, and commissioning was approaching 5%. Train 3 was more than 55% complete, with engineering nearly finished, procurement above 90%, and construction approaching 25%. Train 4 was 22.5% complete, and Train 5 was 14% complete. During the third quarter, electrical, mechanical, and utility commissioning advanced on Train 1.

Matt SchatzmanChairman and CEO

More than 100 operations personnel seconded to Bechtel in the second quarter are working alongside its team and will remain through commissioning and startup to support a smooth transition to operations. During the third quarter, installation and pre-alignment of Train 2's compressor strings were completed, and its main cryogenic heat exchanger was installed. Train 3's first compressor string was set. Foundation pours began for Train 4's main cryogenic rack, along with the excavation of its refrigeration area. Soil stabilization using the deep mixing method began for Train 5. Tank 1 completed intertank nickel plate welding and its first hydrotest. Piling advanced for Tank 3 and began for Tank 4. Site-wide dredging for the berth, turning basin, and channel deepening is complete. The gas inlet facilities are ready for startup, and the Bay Runner pipeline entered service during the third quarter.

Matt SchatzmanChairman and CEO

More than 7,000 workers are now on site each day, with over 70% of them local residents. We are proud to provide safe, high-quality, long-term jobs that make a meaningful impact in the Rio Grande Valley. Across the site, commissioning of systems is underway to support initial hydrocarbon introduction before year-end. We made meaningful regulatory progress during the third quarter. FERC approved our uprate request for Trains 1 through 5, increasing authorized LNG exports from those trains to 30.15 million tons per annum, consistent with our expected annual five-train LNG production. As we mentioned on our last call, in July, FERC released its schedule of environmental review for Train 6, and the final environmental impact statement is expected in June of 2027.

Matt SchatzmanChairman and CEO

In September, the U.S. Army Corps of Engineers authorized a key construction permit for Train 6 in record time, reflecting our team's disciplined preparation and effective regulatory engagement. We are advancing commercial discussions with multiple high-credit quality counterparts for long-term Train 6 LNG offtake. Demand for our long-term LNG for Rio Grande LNG remains strong across a global customer base. Since the Iran conflict began in February, the global LNG market has tightened significantly, and forward prices for 2026, 2027, and beyond have risen. Potential long-term buyers have also placed greater emphasis on energy security and supply diversification. These priorities have been prominent since the Russian-Ukraine conflict began in 2022 and have intensified this year. As we have said, long-term LNG supply from Rio Grande LNG offers buyers an effective combination of attractive pricing and supply security.

Matt SchatzmanChairman and CEO

United States' abundant, diversified natural gas resources and our competitive LNG construction costs support affordable, reliable long-term supply and help protect customers from regional natural gas and LNG price spikes. We expect to advance long-term Train 6 offtake discussions while permitting proceeds, with the goal of securing sufficient commercial support to enable a positive final investment decision, or FID, in the second half of next year. Long-term LNG contract pricing has remained strong since we contracted Trains 4 and 5. Based on current market conditions, we expect Train 6 returns to be at least as strong as those trains. Given that outlook, our goal is to retain a substantial economic interest in Train 6, which NextDecade currently wholly owns. Although we may consider a joint venture tied to a high-quality strategic LNG offtake.

Matt SchatzmanChairman and CEO

We continue to evaluate capital-raising options for our projected Train 6 equity commitment, with a focus on maximizing shareholder value. We expect additional FinCo capacity to fund part of Train 6 equity requirement and are evaluating alternatives for the balance, with a focus on the most accretive per-share solution. Finally, we selected the western end of the Rio Grande LNG site for Trains 7 and 8. We expect to pre-file with FERC before year-end. The schedules place Train 7 and 8 roughly one year behind Train 6 in permitting and development. I will now turn it over to John.

John ZuklicCFO

Thanks, Matt, and thanks to everyone for joining us on the call today. During the third quarter, we continued to execute our project-level balance sheet strategy of terming out bank facility debt through opportunistic debt capital markets transactions, which during the third quarter included approximately $4.1 billion of senior secured notes issued by Rio Grande LNG, LLC, our Phase 1 financing entity. These refinancings extended and staggered our debt maturity profile while also releasing committed bank capacity for financing Train 6 and subsequent expansions. We have now refinanced over $7 billion or 60% of the $11.1 billion of initial capacity under the Phase 1 bank facilities, leaving drawn balances under those facilities of approximately $700 million as of September 30th.

John ZuklicCFO

As we mentioned on our last call, in July, Rio Grande LNG, LLC issued $3.5 billion of senior secured notes in its inaugural 144A offering. These notes, which were rated triple B minus by S&P and Fitch, were issued in four tranches, with maturities ranging from 2031 to 2041 and with fixed rates ranging from 5.15% to 6.15%. We used proceeds from the offering, net of fees, to reduce outstanding balances on the Phase 1 bank facilities.

John ZuklicCFO

In conjunction with the 144A offering and the $1 billion term loan we entered into at a Phase 1 holding company in late June, we unwound a portion of our interest rate swaps associated with the bank debt those transactions repaid, resulting in a $109 million settlement received in July, which we used to further reduce our Phase 1 bank borrowings. In September, Rio Grande LNG, LLC issued another $575 million of senior secured notes in a private placement transaction. The notes, which bear interest at 6.72%, will amortize over a period of approximately 18 and a half years, beginning in June 2029, with a final maturity in December of 2047.

FULL TRANSCRIPT

Continue the full translated transcript in StockNow.

Log in to unlock every statement, the English original, and speaker-by-speaker history.

Log in for the full transcript

Other earnings calls that day

View calls from this day