IREN 2027 Q1 Earnings Call
Review the key takeaways and the transcript of this earnings call.
- AI cloud revenue was $200 million for the September quarter, up 183% quarter over quarter, and total revenue was $228 million, up 66% quarter over quarter.
- Bitcoin mining revenue fell to $28 million as IREN decommissioned mining hardware ahead of GPU installations; the company aims to substantially complete the transition by the end of this quarter.
- Gross margin before depreciation and amortization was 80%, compared with 76% in the prior quarter, while AI cloud gross margin before depreciation and amortization was 86%, consistent with the prior quarter.
- Adjusted EBITDA was $66 million, with a margin of approximately 29% compared with 14% in the prior quarter; net loss was $263 million.
- IREN exited September with $1 billion of operating ARR, and its revenue backlog was over $20 billion, with 2/3 of it with investment-grade customers.
- At September 30th, IREN had $20.6 billion of total assets, including $12.3 billion of property, plant, and equipment, and $5.8 billion of cash, including $2.3 billion of restricted cash.
- Total debt was $10.2 billion, largely in low-coupon convertible notes with maturities concentrated in 2032 and beyond; IREN had approximately $9 billion of cash and undrawn commitments to fund growth.
- IREN spent approximately $5 billion of CapEx in the quarter and had $6 billion of additional planned CapEx to be funded after accounting for cash and committed funding sources.
STOCKNOW INSIGHTS
Continue with outlook and guidance.
Log in to unlock executive comments and Q&A highlights.
Log in for the full summaryStockNow uses AI to translate and summarize earnings calls. Accuracy and completeness are not guaranteed.
Transcript
Preview the first fifteen paragraphs, organized by speaker.
Hello, and welcome to IREN first quarter fiscal year 2027 results conference call. At this time, all participants are in a listen-only mode. After the speaker's presentation, there will be a question-and-answer session. To ask a question during the session, you will need to press star 11 on your telephone. You will then hear automated message advising your hand is raised. To withdraw your question, please press star 11 again. I would now like to turn the call over to Mike Power, Vice President of Investor Relations.
You may begin. Thank you, operator.
Good afternoon and welcome to IREN's Q1 fiscal 2027 results presentation. I am Mike Power, Vice President of Investor Relations, and with me on the call today are Daniel Roberts, Co-Founder and Co-CEO, Anthony Lewis, CFO, and Kent Draper, Chief Commercial Officer. Before we begin, please note that this call is being webcast with an accompanying presentation. For those dialed in by phone, you can elect to ask a question through the moderator after our prepared remarks. I would like to remind everyone that certain statements made during this call may constitute forward-looking statements. These statements are based on current expectations and assumptions and are subject to risks and uncertainties that could cause actual results to differ materially. Please refer to slide two of the accompanying presentation on the Investor Relations section of our website and our SEC filings for more information.
During this call, we will present both GAAP and certain non-GAAP financial measures. Reconciliations of these measures to the most directly comparable GAAP measures are included in the appendix to today's earnings press release and the appendix to the accompanying presentation, both posted on the Investor Relations section of our website. With that, I will turn the call over to Dan Roberts.
Thanks, Mike. Good afternoon, everyone, and thank you for joining us. During the quarter, we signed new multi-year contracts, including with a leading frontier AI lab, taking revenue backlog to over $20 billion, two-thirds of it with investment-grade customers. We closed GPU financing that, with customer prepayments, funds more than 100% of the GPU CapEx for the Mackenzie deployments. We handed over Horizon 1 to Microsoft with NVIDIA Exemplar Cloud status. Finally, we advanced construction of new data center campuses across the globe, including our flagship 2 GW Sweetwater hub. Compared to the last quarter, AI Cloud revenue nearly tripled to $200 million. Operating ARR doubled to $1 billion, and adjusted EBITDA margin went from 14% to 29%. One date has moved, so let me deal with it first. In July, we said more than $4 billion of operating ARR was targeted to be online by year-end.
It's now January. Two reasons. One, a customer asked for a design change, which we agreed to, and it sits outside the original scope. And two, supplier timing. The data centers are practically done, and we're waiting for remaining equipment to arrive to finish commissioning. If suppliers deliver, we're targeting January. If they're late, as suppliers have been across the industry this year, it may run to the end of February. Building at this scale is complex, and even more complex when you own every layer: land and power, data centers, compute, and the people to bring it together. We've spent years building all of it. Today, we run three businesses, summarized on slide four of our presentation. First, AI Cloud. $1 billion of operating ARR today. More than $4 billion contracted and fully funded, ramping as the remaining capacity is commissioned. Second, the data centers. $6 billion of data center assets today, $10 billion targeted by June next year. 20-year assets that can carry several generations of compute, cash-funded to date, and unencumbered.
Third and final, land and power. More than 30,000 acres across global markets, supporting both over 5 GW of secured power and more than 35 GW in development. Many of those are early stage, and not all of them will convert to grid connection agreements. Securing land and power ahead of demand is what we've done since day one, and it's why the platform today spans three continents. Most companies do one of those three. We do all three, which keeps more of the economics with us, gives us more ways to fund growth, and more control over delivery. Demand for compute hasn't slowed.
Since quarter end, we've signed contracts at $22 million of annualized revenue per megawatt of IT load on a five-year term, and in excess of $40 million per megawatt on a shorter duration contract. Importantly, the five-year agreement also includes a customer prepayment covering approximately 90% of the associated GPU CapEx. We've also expanded our AI Cloud contract further with the same leading AI frontier lab and contracted H100s at double the original pricing. That's the pricing backdrop for contracting our Vera Rubin capacity. Capital markets have become more selective in the last few weeks, and the questions have undoubtedly moved from how big the contract is to whether it can be delivered, financed, and run at a profit. Those are the right questions, and this quarter for us answers them. Horizon one went from civils to an NVIDIA Exemplar Cloud-validated GB300 cluster in about 14 months.
JLL puts the global average at 18 months to build a 50 MW data center, and that's the building alone. We delivered the building and the cluster inside it four months faster than that benchmark. I'll come back to what that last stage involves. Operating capacity rose 127% in the quarter to 0.1 GW. We raised $19 billion in the 12 months to September, including $6.5 billion of GPU financing since May at 6%-9.5%. Our AI Cloud ran at an 86% gross margin, in line with last quarter. Now, this is where IREN differs from a typical neocloud. We don't lease someone else's data center and carry the liability on our balance sheet. We secure the power, we develop the land, we build the infrastructure, and we deploy the compute. Each deployment leaves us with long-term assets we own.
Owning the power, the land, and the data centers also means we set the pace. We want to build as fast as demand allows, but we are not obligated to develop every site at once. The power is secured, and the data centers are ours, so we do not sign contracts or raise capital to cover lease payments. Investment and contracting decisions are made on risk-adjusted returns, financing conditions included, and the economics justify building. During the quarter, average revenue per megawatt on our three and five-year contracts continued to increase, now supporting GPU paybacks of around 18 months, or even lower depending on the level of customer prepayments. At Mackenzie, customer prepayments and GPU financing together covered more than 100% of the associated GPU CapEx. The contracts signed since quarter end reinforce that picture, attractive pricing alongside customers funding a substantial portion of the GPU CapEx.
As we add capacity, we are strengthening how we deploy and how we operate it. Our work with NVIDIA and the Mirantis and k0rdent AI teams is improving how we provision, manage, and support these environments. Existing customers are renewing and expanding with us. New logos are proving demand, and the renewals are proving ongoing delivery. Now, to delivery on the ground. Slides 13 and 14 of the presentation show progress site by site on our targeted expansion to 0.8 GW by the end of 2027, and data center expansion beyond that. The initial 0.3 GW is in the final stages, and construction for further capacity is underway across six sites. That last mile is the most complex. It is the part you do not see from the drone photos.
GPUs racked, miles of fiber pulled, whole clusters connected and tested, and the data center business handing over to the AI Cloud business. The expertise behind these deployments is also shaping the next generation of AI factories. Led by our Chief Innovation Officer, John Gross, we are working closely with NVIDIA to advance data center design and develop even faster ways to build. That work also means getting more out of the sites we already own, using power headroom within existing connections to support more compute. Mackenzie is the example, 100 MW of power secured, mass grading now started for new liquid-cooled data centers, built to the same design we have already delivered. Slide 17 shows the pipeline behind the data center and AI Cloud businesses I just described. Our development team keeps originating sites ahead of the next phase of growth.
Those more than 30,000 acres span North America, Europe, and Asia Pacific. That gives us choices about where we serve customers and where we progress sites as local conditions allow. We do not need every market to move at the same pace. Where we build is just as important as how we build. We focus on rural locations with appropriate setbacks from neighbors and engage with communities and regulators before progressing grid applications to understand local priorities from the outset. Our recently announced 900 MW Redbank site is a good example of this in Australia. We hire locally, we work with local suppliers, and we prioritize bringing water to site for our closed-loop cooling systems to reduce reliance on local supplies. We want our projects to bring lasting jobs and investment to these communities while respecting the needs of the people who live there.
We are being deliberate about how we grow, contracts with customers who renew, returns that justify the capital, and the financing attached to each deployment. With that, I will hand over to Anthony to walk through the numbers and how we are funding the next phase.
Thanks, Dan, and good evening, everyone, and thank you for your attendance. Starting with our results, we delivered another quarter of significant growth in AI Cloud revenue, supported by continued execution. AI Cloud revenue was $200 million for the September quarter, up 183% quarter-over-quarter, reflecting the continued deployment and monetization of our data center and GPU capacity. Total revenue was $228 million, up 66% quarter-over-quarter, with Bitcoin mining revenue falling to $28 million as we continue to actively decommission Bitcoin mining hardware ahead of GPU installations. We aim to substantially complete this transition by the end of this quarter. Gross margin before depreciation and amortization was 80%, up from 76% in the prior quarter, as AI Cloud revenue represented a larger share of total revenue. AI Cloud gross margin before depreciation and amortization was 86%, consistent with the prior quarter.
FULL TRANSCRIPT
Continue the full translated transcript in StockNow.
Log in to unlock every statement, the English original, and speaker-by-speaker history.
Log in for the full transcriptCall participants
13 people spoke on this call — only 2 are shown here.
PARTICIPANT LIST
View participant details in StockNow.
Log in to see executives and analysts, their roles, and complete speaking history.
Log in to view all participantsKeep exploring