Fermi 2026 Q3 Earnings Call

Review the key takeaways and the transcript of this earnings call.

PeriodQ3 2026Duration43 minParticipants13

Transcript

Preview the first fifteen paragraphs, organized by speaker.

Operator

Good morning, and welcome to Fermi America's Third Quarter 2026 Earnings Call. At this time, all participants are in a listen-only mode. We will open up the floor for your questions after the presentation. If you wish to join the queue to ask a question at any time, you can press star one. Should you wish to remove yourself from the queue, press star two. It is now my pleasure to turn the floor over to your host, Rodrigo Acuna, Director of Investor Relations.

Rodrigo AcunaDirector of Investor Relations

The floor is yours. Good morning, and welcome to Fermi America's Third Quarter 2026 Earnings Call.

Rodrigo AcunaDirector of Investor Relations

I'm Rodrigo Acuna, Director of Investor Relations. With me today are Lee McIntire, our Chief Executive Officer, Rob Masson, our Chief Financial Officer, and Anna Bofa, our Chief Commercial Officer. Later in the call, we'll be joined by Marius Haas, our Chairman of the Board, and Jacobo Ortiz, our Chief Operating Officer. Today's remarks include forward-looking statements. They are subject to risk and uncertainties that could cause actual results to differ materially. Please see the risk factors in our Form 10-K, Forms 10-Q, and other SEC filings. We will also discuss non-GAAP measures. Definitions and related disclosures are in our investor presentation. After our prepared remarks, we will take your questions. Now, I'll turn the call over to Lee.

Lee McIntireCEO

Thanks, Rodrigo. Good morning, everyone. This is my first earnings call as CEO. I want to use it to tell you where we're taking Fermi and how we'll get there. Let me start with the environment we're operating in for context. In the past couple months, there's been significant change in the market. Power got more scarce. State by state, moratoriums tightened up access to electrons, and in Texas, ERCOT, for example, froze new large load connections, which are powering AI data centers. Land got harder to find. Community angst about the spread of data centers, concerns about water, noise, light, and the natural environment have taken many sites off the table. Permits are harder to come by. Texas, for example, paused new air permits before the election, and then the elections last week added more uncertainty. As a result, the gates to first power got harder to clear.

Lee McIntireCEO

That's driving demand higher for safe harbor sites where the region benefits from jobs, economic development, and long-term investment. That's bringing investment-grade hyperscalers to our door. We've also seen shifts in how AI infrastructure gets financed. The high-yield bond market has tightened. We feel more hyperscalers are moving away from neoclouds toward direct relationships. As this shift is occurring, we're focusing our commercial work on deals directly with investment-grade hyperscalers. Against that backdrop, we made two announcements this morning. The TensorWave lease will not move forward. That deal was a complex Turnkey lease with a neocloud involving multiple parties and requiring the support of third-party credit. Most importantly, today, we've reached an exciting agreement with an investment-grade hyperscaler for 600 MW of our 2027 power capacity. It's a simpler deal, providing power to a single customer with less to finance.

Lee McIntireCEO

It's a stronger deal on every measure that matters to us. It's nearly three times the capacity. It's with an investment-grade hyperscaler directly, so it doesn't depend on anyone else's credit. The customer is building its own data centers on our Project Matador, so Fermi doesn't carry that construction capital requirement. Importantly, it's putting capital up front to accelerate construction. These consist of a $200 million prepayment agreement. It provides substantial upfront funding for the 600 MW development, and an early construction and site development agreement that sets framework to start site preparation. We're excited about the structure of this deal, and it comes with little or no dilution. This is our strategy in practice. We invested early to getting the site ready. That lets customers build faster, brings their capital in earlier, and turns their power and infrastructure advantages into long-term revenue opportunities.

Lee McIntireCEO

We continue to work towards a definitive long-term lease, and the customer's identity remains confidential. Our advantage isn't just that we have power, it's that we've done the work to help customers turn access to power into operating data centers faster. That work extends to the ground we're building on. Our campus is on land leased from Texas Tech University System. In this market, that partnership is even more valuable. Earlier this week, Texas Tech Chancellor Brandon Creighton reaffirmed that the university, quote, "remains firmly committed to the success of Project Matador," unquote. When community concerns are taking sites off the table, that kind of institutional backing is part of what we believe makes our site a safe harbor. We have the power, the land, and the permits in hand as many of our competitors face strong headwinds. We've invested more than $1.6 billion in the site.

Lee McIntireCEO

We've done the long lead work ahead of lease construction, engineering design, site preparation, and moving equipment to site, which reduces execution risk for our customers and our lenders. On permits, we have air permits for 6 GW in hand. We have a comprehensive water strategy built around conservation. We've designed the project to minimize water use by maximizing dry and hybrid closed-loop system. When we're running at capacity, we expect to use about 80% less water than traditional methods. For fuel, Energy Transfer has committed up to 220,000 MMBtu of natural gas per day. We've installed 4.6 miles of onsite pipeline, rated at 450 million cubic feet per day. That's plenty for 2 GW. On power, we're bringing our own. Behind-the-meter, on our own grid, we have more than 2 GW of generation equipment secured. Many in the Panhandle community are supportive of this project.

Lee McIntireCEO

Lastly, where our competitors are struggling to source equipment, we already have turbines on site. Those advantages are hard for others to replicate. We have a robust pipeline of customers who see this. Our disciplined capital management puts us in strong position to evolve Fermi from pre-revenue, pre-lease to our next phase. Now I'll turn the call over to Anna, who will walk you through how we're building our customer portfolio.

Anna BofaChief Commercial Officer

Thanks, Lee. I am really excited about the commercial progress we are making at Fermi, and I want to spend a few minutes talking about why this hyperscaler relationship is so significant and what we are seeing across our broader customer pipeline. Power has become one of the defining constraints on AI growth, and it is no longer just about how much power you can deliver. It is about how quickly, how reliably, and whether you have the infrastructure in place to support development at scale. One thing has become increasingly clear in our conversations with the world's largest technology companies. Customers are no longer waiting for power to come to them. They are building around where power is available. The 600 MW commitment Lee just described is a great example of this shift.

Anna BofaChief Commercial Officer

We have spent months working closely with this customer's commercial and technical teams, listening to their requirements, understanding their development timelines, and aligning our plans around what it will take to bring capacity online as quickly as possible. What is particularly exciting is how we have been able to align around what each side does best. These are sophisticated customers. They have their own engineering standards, building designs, construction teams, and capital. They do not necessarily need us to build their data centers for them. What they need is reliable power, development-ready land, and a partner who can help them move faster. That is precisely what our Powered Land+ offering is designed to provide. Fermi brings the power, the land, and the supporting campus infrastructure. Our customers can bring their own designs and construction capabilities, allowing us to move forward together faster without Fermi having to finance and deliver the entire data center.

Anna BofaChief Commercial Officer

In this case, we have gone a step further. We have already advanced engineering and design work with our partners, and we secured critical long-lead materials ahead of the customer's final lease. Structural steel is a great example. Rather than having to start a new procurement cycle, this customer can leverage the steel we have already secured to accelerate its construction schedule. That is the value of the infrastructure work we have done in advance and why being ready matters so much in this market. The preparations ahead of finalizing the long-term lease. To me, that speaks to both the urgency of demand and the strength of the partnership we have built. We are targeting initial power availability in late Q2 or early Q3 of 2027, and the customer is aligning its development plans with that schedule.

Anna BofaChief Commercial Officer

For Fermi, this creates the opportunity to bring our power capacity into revenue sooner while deploying less capital into customer-owned data center construction. Importantly, we believe this approach can be replicated. Our pipeline is strong, with active discussions across multiple investment-grade hyperscalers. If the opportunities we are pursuing today convert into definitive agreements, they could absorb our planned 2.2 GW of capacity, and our broader pipeline extends several gigawatts beyond that. We are also seeing customers think well beyond their initial deployment. They are asking about future expansion rights and how they can grow with us as additional power becomes available. That is central to how we envision Project Matador developing. Our strategy is to anchor the campus with four to five investment-grade hyperscalers, each able to establish an initial presence and expand over time.

Anna BofaChief Commercial Officer

That creates the potential for a diversified long-term customer portfolio, greater visibility into demand, and a more disciplined approach to planning and financing future infrastructure. Our focus now is execution, converting our pipeline into financial commitments and long-term agreements, aligning customer construction schedules with our 2027 and 2028 power ramp, and bringing capacity into revenue as quickly and responsibly as possible. Ultimately, we are not simply selling megawatts. We are building the infrastructure and partnerships that enable some of the world's largest technology companies to accelerate their ambitions. We have established the foundation. Now we are seeing customers begin to build on it. With that, I will turn it over to Rob to explain how our three commercial offerings and broader capital strategy support that growth.

Rob MassonCFO

Thank you, Anna, and good morning. Today, I will cover our third quarter results, our liquidity, our capital strategy, and our covenants. Before I do that, I want to build on Anna's comments and talk about the multiple options Fermi has to create differentiating value. This quarter, we shared our business strategy that aligns our pricing, cost, and capital requirements for the long term. You can see this strategy in action with the recent news, which is tightly aligned with today's market, the capital-raising environment, and what our customers need. It is the right approach for this early stage of our business. Fermi creates value two ways under one triple net lease. We sell private behind-the-meter power, and we lease data center real estate on our campus. Each has a fixed charge and a variable charge.

FULL TRANSCRIPT

Continue the full translated transcript in StockNow.