TeraWulf 2026 Q3 Earnings Call
Review the key takeaways and the transcript of this earnings call.
- Third-quarter revenue was $76.2 million, compared with $44.8 million in the second quarter; HPC lease revenue increased 97% quarter over quarter to $63.0 million and represented approximately 83% of total revenue.
- Third-quarter results reflected 102 critical megawatts operating and generating lease revenue at Lake Mariner after the CB3 lease commenced on July 13th.
- GAAP net income attributable to TeraWulf was $709.9 million, compared with a net loss of $939.9 million in the second quarter, primarily reflecting a non-cash fair value adjustment associated with Google warrants and a gain on sale of equity interest in the Abernathy joint venture.
- Non-GAAP adjusted EBITDA was negative $12.8 million, compared with negative $18.3 million in the second quarter.
- Cash and restricted cash totaled approximately $2.4 billion as of September 30th; TeraWulf had approximately $1.1 billion at the parent level and approximately $1.2 billion of gross cash at Wulf Compute.
- The revolving credit facility was amended after quarter end, increasing commitments from $250 million to $400 million, with an incremental $150 million accordion feature for a total size of $550 million; the $150 million LC sublimit was eliminated.
- Approximately $2.9 billion of Wulf Compute project capital expenditures had been completed, with approximately $1 billion remaining; approximately 2/3 of the remaining capital expenditures were committed.
STOCKNOW INSIGHTS
Continue with outlook and guidance.
Log in to unlock executive comments and Q&A highlights.
Log in for the full summaryStockNow uses AI to translate and summarize earnings calls. Accuracy and completeness are not guaranteed.
Transcript
Preview the first fifteen paragraphs, organized by speaker.
Greetings, and welcome to the TeraWulf Third Quarter 2026 Earnings Conference Call. At this time, all participants are in a listen-only mode. A brief question-and-answer session will follow the formal presentation. If anyone should require operator assistance during the conference, please press star 0 on your telephone keypad. As a reminder, this conference is being recorded. It is now my pleasure to introduce your host, John Larkin, Senior Vice President and Director of Investor Relations with TeraWulf. Thank you. You may begin.
Thank you, operator. Good morning, and welcome to TeraWulf's Third Quarter 2026 Earnings Call. Joining me today are our Chairman and CEO, Paul Prager, our CTO, Nazar Khan, and our CFO, Patrick Fleury. Before we begin, please note that our remarks today may include forward-looking statements. These statements are subject to risks and uncertainties, and actual results may differ materially. Words such as anticipate, expect, believe, intend, estimate, project, could, should, will, and similar expressions are intended to identify forward-looking statements. For a discussion of these risks, please refer to our filings with the SEC, available at sec.gov, and in the Investor Relations section of our website. We will also reference certain non-GAAP financial measures. Reconciliations to the most comparable GAAP measures are available in our earnings release and filings. With that, I will turn the call over to our Chairman and CEO, Paul Prager.
Thanks, John, and good morning, everyone. On Wednesday, we announced two important milestones at Justified: Google's credit support in connection with the financing of our $19 billion Anthropic lease, and a definitive EPC agreement with Fluor for the development of the campus. I want to start there, because those agreements directly address two of the biggest questions facing our sector today: How do you finance infrastructure of this scale efficiently, and how do you manage the execution risk associated with building it? There has obviously been significant volatility across AI infrastructure. Investors are focused on higher financing costs, leverage, the amount of capital being deployed across the sector, and whether the returns ultimately justify that investment. Those are legitimate questions, and we are highly aware of the environment. Credit spreads have moved, and there is a significant amount of infrastructure financing coming to the market.
At the same time, demand for compute remains extremely strong, deliverable power remains scarce, and our customers continue to make very substantial long-term commitments. This brings me to our Justified data campus in Hawesville. We already have the equity required to fund the project. Google's credit support materially strengthens the financing profile, and we fully expect to fund the remaining capital requirement with project-level debt, with contractual protections in place to preserve our returns. We have always believed in raising capital when you can, not when you have to. We did just that. We have the equity, we have the customer, and we have the credit support and a clear path to competitive long-term debt financing. We structured this transaction from the beginning so that financing risk would not get pushed onto TeraWulf's shareholders. We protect our economics. That is fundamental to how we operate.
The Fluor agreement addresses the other side of the equation: execution. We know firsthand how difficult these projects are to build, because we are doing it at Lake Mariner. We understand the labor, procurement, electrical infrastructure, cooling, commissioning, and customer coordination involved in delivering capacity at this scale. At Justified, we made a deliberate decision to pair that experience with one of engineering excellence and one of the strongest construction organizations in the world. The definitive EPC agreement covers all three data center buildings and expands Fluor's role from early engineering and pre-construction into engineering, procurement, construction, testing, and commissioning. It includes defined delivery milestones, open-book cost reporting, procurement oversight, and contractual cost and schedule protections, with guaranteed maximum pricing being established as engineering and procurement progress. That gives us substantially greater execution capacity without trying to build a global engineering and construction organization within TeraWulf. Construction is already progressing. Pilings are underway, and we continue to target phased ready-for-service deliveries beginning in late 2027 and continuing through the second quarter of 2028.
We also continue to expect project costs to remain within the approximately $10 million-$12 million per critical IT megawatt range, which we have previously discussed on a comparable basis. When you look at Justified today, we have a world-class customer in Anthropic, approximately $19 billion of contracted revenue. Investment-grade credit support from Google, the equity required, an experienced EPC partner in Fluor, and a clear path to project-level debt financing. Of equal import, we also enjoy a fantastic regulatory framework in Kentucky. Congressman Brett Guthrie stated, "This historic investment in Hancock County is a great example of what's possible with a collaborative community-first approach to data center development.
I am confident this project will serve as a national model for communities looking to grow their economies, participate in the industry of the future, and improve the well-being of their residents." Justified is not a theoretical development. It is contracted infrastructure that we are building to deliver. Lake Mariner is where you can already see that model working. CB3 is online and generating revenue. CB4 is moving into commercial operation, with the remaining data halls scheduled to come online sequentially through the end of the year. CB5 follows beginning in January, with phased delivery targeted through the end of the first quarter. By the end of Q1, we expect approximately half of our contracted critical IT capacity to be operating and generating revenue, and we expect to exit the quarter with approximately $700 million of annualized run rate leasing revenue. That is an important milestone for TeraWulf.
For the last several years, investors have largely been valuing what we were building. Increasingly, our investors will see these contracts convert into operating infrastructure, recurring revenue, and cash flow. We continue to expect Lake Mariner to be delivered close to the midpoint of our original $8 million-$10 million per critical IT megawatt cost guidance. We told investors what we expected it to cost, and we are delivering against that expectation. Nazar Khan will give you more detail on both Lake Mariner and Justified in just a moment. The larger point is simple. Contracted megawatts are becoming operating megawatts. Operating megawatts are becoming revenue, and revenue is becoming cash flow. That is execution. It is also important to understand the business we are building. TeraWulf is not a neocloud. We are an energy infrastructure company.
We control the land and power, develop and operate the infrastructure, and lease that capacity under long-duration contracts. We do not own the GPUs. We do not take technology risk where the chip may win or may not in the next generation of AI. Our job is to secure scarce power, build high-quality infrastructure around it, contract that capacity with strong customers, finance it efficiently, and generate durable cash flow. We have been developing and financing large-scale energy infrastructure for decades. This is what we know how to do, and we are building a business, not collecting megawatts. Growth only matters if it creates cash flow and equity value for our shareholders. That discipline is particularly important in the current capital markets environment. Higher financing costs matter, and we factor them into every new transaction. As construction costs, tariffs, financing costs have changed, our contract economics have changed with them.
We are not going to absorb financing risk that belongs somewhere else in the structure, and we are not going to accept a bad return simply to announce another lease. There is another side of that equation, and that's the cost of waiting. For frontier AI companies investing billions of dollars in compute, six months matter. 12 months matters enormously. When time to market is critical, the value of real, deliverable power increases significantly. That brings me to Muskie. We continue to be extremely excited about Muskie, and there is no doubt this site in Kentucky is far more valuable today than it was at the beginning of the week. Muskie has scale, investment-grade utility partners in Kentucky Power and AEP, front-of-the-meter grid service, attractive power economics, and a highly supportive state and local environment.
Most importantly, we now have a contracted path to the initial gigawatt of electric service. That is real, deliverable power. A piece of land next to a transmission line is not a data center, and a queue position is not power. The questions we care about are straightforward. When does the power actually show up? Who is responsible for building the infrastructure? What approvals are in place? What does the energy cost? Can the developer actually execute? At Muskie, we are working closely with Kentucky Power and AEP on opportunities to accelerate portions of the development schedule, including potentially pulling forward that second 500 MW. At the same time, our view of the ultimate scale of Muskie continues to increase, and the level of customer interest we are seeing reinforces that conviction.
We are in active discussions with a number of very high-quality prospective customers, and one of the questions we get asked is how we think about customer diversification. Diversification is clearly valuable. We understand the benefit of adding another large, high-quality customer to the portfolio, but you cannot look at diversification in a vacuum. There can be meaningful economic differences between leasing to a hyperscaler and leasing to a frontier model company. The credit profile may be different, the financing may be different, but the rent, yield, and return on our invested capital can also be materially different. Team and culture matter as well. When you are entering into a long-duration relationship, alignment, speed of decision-making, and the ability to work through issues together can have a significant impact on execution and ultimately on returns. We weigh all of it. What is the rent? Who is the credit?
What does it cost us to finance? How much capital do we have to put in? What protections do we have? What's the duration of the deal? Ultimately, what is the risk-adjusted return to our shareholders? My job is to make the decision that creates the greatest risk-adjusted value for TeraWulf shareholders, and I take that seriously. Justified is a good example. We have a frontier AI customer with very attractive long-term lease economics, paired with investment-grade credit support from Google. At Muskie, we have something equally valuable: scale, power, and time. That gives us options. It allows us to be patient and disciplined about the selection of a customer, the terms, the credit structure, and the economics, rather than feeling pressure to just sign the first available tenant.
I am not going to predict when we sign the next lease or who that customer might be, but I am highly confident that Muskie will deliver, highly confident in the level of customer interest, and highly confident that we could structure a transaction that reflects the value of this important asset. Just as importantly, we are not going to sign a lease that forces us to issue equity at a valuation we do not believe reflects the value of the company. The commercial structure, customer economics, and financing plan, they have to work together. We will bring that home. Our objective is to structure a financing solution that recognizes the value we've created at Muskie, preserves attractive returns, and minimizes dilution to our shareholders.
Development will be phased, capital will be raised and deployed alongside contracted demand, and we will remain intensely disciplined about protecting the balance sheet as we grow. More broadly, we remain confident in our target of contracting an incremental 250-500 MW of critical IT capacity annually. Importantly, we believe that we can achieve that target with the portfolio we control today. We do not need to buy sites simply to make our pipeline look bigger. Any new opportunity has to have real power and compete for our capital and create value for our shareholders. Do we control the power? Can it scale? Can it be delivered when the customer needs it? Can we finance it intelligently, and can we earn a compelling return? The same discipline applies to regulation and the communities where we operate.
FULL TRANSCRIPT
Continue the full translated transcript in StockNow.
Log in to unlock every statement, the English original, and speaker-by-speaker history.
Log in for the full transcriptCall participants
15 people spoke on this call — only 2 are shown here.