Matt SummervilleSenior Research Analyst

Good afternoon, everyone. Thank you for joining us today. Matt Summerville here with D.A. Davidson, the covering analyst for MP Materials at our first D.A. Davidson Critical Minerals Conference being held virtually on Monday, November 9. With me today from MP Materials is Ryan Corbett, the company's Chief Financial Officer. For the next 40 minutes, I will be hosting a fireside-style chat with Ryan. Should you wish to submit a question, you should be able to do so electronically, and it will register on my screen, and I will be happy to ask on your behalf. Ryan, why don't we go ahead and get started? With NdPr production, I want to start in the midstream.

Matt SummervilleSenior Research Analyst

With NdPr production recently exceeding a monthly run rate of 450 tons for portions of the third quarter just reported late last week, your expectation is to operate above 5,000 metric tons in 2027. What are the most important remaining steps to consistently reach that initial 6,000 ton, I don't want to use the word nameplate, but that initial 6,000-ton target? Is it the separation cell circuit uptime recoveries? Help understand the remaining pieces to that puzzle, so to speak.

Ryan CorbettCFO

Sure. Yeah, and thanks, Matt, for having me. Happy to be here. Yeah, happy to dig into that. Obviously, we covered a lot of this on the earnings call last week, and I think overall, to put in perspective where we're at, I think we're incredibly pleased with the progress. I think Michael gave a great assessment of progress to date. I think his point really in operating north of that level for portions of Q3, I think from our perspective in looking at the progress that we've made on de-bottlenecking, in a lot of ways, we're effectively there.

Ryan CorbettCFO

I think the guidance for next year of between 5,000 and 6,000, the major delta between being at 6,000 versus being at 5,000 is not really indicative of confidence in continued de-bottlenecking, which, for context, if you look at a production line chart from when we started in very, very late 2023 to where we are today, it's basically up and to the right with the typical sort of step backs for the biannual plant shutdowns and turnarounds. I think that we feel very good that we continue to be on that path. The typical remaining items that you see primarily for us are materials handling that we've talked about.

Ryan CorbettCFO

With any complicated process like rare earth refining, what always ends up happening is once you reach sort of your targeted throughput levels and you take another step up, you always find maintenance items to address to ensure that you're maintaining the uptime that you want at those increased throughputs. That has sort of been the consistent story over the last two years of getting to this level. There's nothing new here. This is sort of just a continuation of what we've been executing on, and I think executing very well for the last couple of years. The major item that we will see early next year, which again, is not really impactful from a throughput perspective, but of course, the numbers that we report out are a combination of throughput and uptime.

Ryan CorbettCFO

What we will be doing early in the year is bringing the first train of our chlor-alkali facility online, which is a project we've been talking about for quite a while, and we're very, very encouraged by the progress, and looking forward to getting that online. That will involve incremental downtime, particularly in the early part of the year. We talked about our progress on heavy rare earth separations as well, which as that ramps up and we add incremental capabilities there, could have some impact, I think, much less meaningful than chlor-alkali. You put all of that together, and that's sort of what led us to that guidance level for next year.

Matt SummervilleSenior Research Analyst

Let's spend a minute kind of double-clicking on chlor-alkali. Can you walk through how that sort of phases in over the course of 2027, and if round numbers, you were at an all-in production cost of somewhere around $65-$67 a kilogram, just round numbers, this last quarter, where would you think you can get to in 2027 as a function of chlor-alkali?

Ryan CorbettCFO

Sure. I think that to give background on chlor-alkali, right now from the perspective of our current cost structure, hydrochloric acid and caustic soda are a very, very significant portion of the cost structure for rare earth refining. We are benefiting from hundreds of millions of dollars of investment in an existing chlor-alkali facility, and we've continued to invest in that, literally taking the thing apart bolt by bolt, put it back together for recommissioning. We're at the point where the facility has three trains. We're going to bring the initial train online early in the year, and it's a major project. If you think about how we're dealing with waste right now, we talked many years ago about the salt crystallizer and the brine purification processes we'd put in place.

Ryan CorbettCFO

We will tie this into existing brine purification and brine treatment because the beauty of chlor-alkali is you are effectively using the waste off of the refining process as your feedstock to recreate the chemical reagents that are critical to feed the process. It creates sort of this beautiful closed-loop system. We wanted to ensure that we did that thoughtfully and didn't do it all at once in order to ensure that we maintain the types of uptimes that you see us reporting today. What we will see early in the year is bringing that initial train on. We need to do those tie-ins into the existing shared infrastructure for the plant. In addition, chlor-alkali is a pretty significant power consumer.

Ryan CorbettCFO

That is one thing that in order to get all of these tie-ins done right and launch the process safely and effectively, we will have to take parts of the plant down where there is shared electrical infrastructure and then bring it back online. That really is driving the view early in the year. I think from our perspective, we are a very significant consumer of these reagents. We are one of the largest in the U.S. Having the redundancy and resiliency of producing these chemical reagents ourself and, of course, doing it from product that is effectively salt water that otherwise would get evaporated, I think is a fantastic improvement to not just cost structure, but security of supply chain, redundancy, resiliency, et cetera.

Ryan CorbettCFO

I would say if you look at where we sit today from a cost structure perspective in the low 60s, I think the two meaningful drivers that we expect to see over the next several quarters are, right now, in the last quarter we reported producing just above 1,000 tons in the quarter. There continues to be really significant economies of scale from fixed cost absorption as we get closer to that 1,500 tons a quarter. We have sort of given some rough detail on fixed versus variable. You can do the math on, given the scale of Mountain Pass and all of the shared infrastructure that is present, power plant, water treatment plant, the maintenance team, et cetera, there is a really significant amount of fixed costs that will continue to get leveraged across a much higher production number, which I think will continue to drive the cost down.

Ryan CorbettCFO

The chlor-alkali plant, from a direct cost reduction perspective, we haven't given specific numbers. The reality is we want to get the plant and the initial train running before we get into a ton of specifics. Just given the significance of that input to our cost formula and our confidence in our ability to produce those reagents at a much lower cost than we are able to buy from the market, that will have a significant benefit. The thing to keep in mind, of course, as I mentioned, there are three trains here. We are starting with one, so we will need to feather in the incremental capacity over time and continue to monitor the external market to make sure we are doing things efficiently and effectively.

Ryan CorbettCFO

But undoubtedly, you look at the combination of those two things, particularly as we get into the back half of the year where some of the incremental downtime and things like that will not be a part of the equation the way they are in the beginning of the year, we have a lot of confidence in continuing to drive the cost structure down. The last element to that from a cost structure perspective is, you think about all the other things that we're doing at Mountain Pass. You've got recycling, you've got heavy rare separation, you've got the early costs for chlor-alkali that aren't producing a benefit yet. And you've got all of these incremental products that we've been talking about. We have gadolinium separation coming online in 2028, samarium separation coming online in 2028.

Ryan CorbettCFO

You have existing dysprosium and terbium production that will be in commercial form this quarter. None of those products at this point are absorbing any of the shared infrastructure costs that's present at the site. And so, every dollar of cost is being costed into the NdPr equation. And so, as you sort of broaden the product portfolio, I think the reality is if you look at this and you look at, for example, the sale we made this last quarter of our SEG+ product, you see the fact that in a lot of ways, NdPr has been carrying the cost of some of these other products over the last several years. And the margin profile of some of these other products is excellent.

Ryan CorbettCFO

As we get into production of some of these other products, naturally, you will start to get some benefit on the NdPr side as well. So, there's really three obvious vectors for us to continue to drive the cost structure down on an NdPr basis.

FULL TRANSCRIPT

Continue the full translated transcript in StockNow.

Access every statement, the English original, and speaker-by-speaker history with StockNow Pro.

View the full transcript with Pro

Other earnings calls that day

View calls from this day