Ionic Digital 2026 Q3 Earnings Call
Review the key takeaways and the transcript of this earnings call.
- Ionic Digital Inc. reported 3rd quarter 2026 revenue of $49 million, including approximately $44 million from digital infrastructure leasing and $5 million from Bitcoin mining.
- Gross profit was $39 million, adjusted gross profit was $44 million, and adjusted gross margin was 89%; digital infrastructure margins were 99%, while the mining segment was approximately breakeven at the gross margin level.
- G&A was $26 million, including $12 million of non-recurring direct listing costs and $5 million of non-cash stock-based compensation; excluding those items, G&A was approximately $9 million.
- Net income was $17 million, or $0.38 per diluted share, and adjusted EBITDA was $35 million with a 71% margin; year-to-date adjusted EBITDA was $108 million.
- Capital expenditures were $7 million in the quarter, primarily for equipment related to the Ward County substation expansion.
- Ionic ended the quarter with no debt, $381 million in cash, and 2,954 Bitcoin valued at $247 million, for total liquidity of approximately $628 million.
- Since quarter-end, Ionic sold 737 Bitcoin, approximately 25% of its holdings, for net proceeds of approximately $62 million; pro forma cash was $443 million and remaining Bitcoin was valued at $185 million based on September 30th prices.
STOCKNOW INSIGHTS
Continue with outlook and guidance.
Log in to unlock executive comments and Q&A highlights.
Log in for the full summaryStockNow uses AI to translate and summarize earnings calls. Accuracy and completeness are not guaranteed.
Transcript
Preview the first fifteen paragraphs, organized by speaker.
Good day, and welcome to Ionic Digital's third quarter 2026 earnings call. At this time, all participants are in a listen-only mode. After the speaker's presentation, there will be a question-and-answer session. To ask a question, you will need to press star 11 on your touch-tone telephone. Please note, this call is being recorded. I would like to turn the call over to Hannah Stuckey, Director of Investor Relations.
Please go ahead. Good afternoon, and welcome to Ionic Digital's third quarter 2026 earnings call.
With me today, we have Chief Executive Officer Andy Stewart and Chief Financial Officer Chris Hickman. Before we begin, a brief reminder. Statements made on today's call, in our presentation, and in our press release contain forward-looking statements. Actual results may differ materially. These statements are subject to the risks described in the risk factor section of our prospectus and our subsequent filings with the SEC, which you should read in full. We undertake no obligation to update these forward-looking statements except as required by law. For additional information on non-GAAP financial measures discussed on today's call, please refer to the reconciliations to the most directly comparable GAAP measures. These reconciliations are available in today's earnings release and investor presentation, both of which can be found on the investor relations section of our website.
With that, I'll turn the call over to Andy.
Thanks, Hannah, and good afternoon, everyone. We know there's been quite a bit of conversation on the latest political cycle in Texas, and we'll make sure to touch on that later. I'll start today with our results released this afternoon. Our third quarter was in line with our expectations, and I'm pleased with the progress we're making on our top priority, which is putting the remaining capacity at Ward County and Midland under contract. There are a number of initiatives we're working on to achieve that goal: the ERCOT process for Ward County, the land work at Midland, and working with prospective customers on the scope and design they need. We made solid progress in all three during the quarter, and I'll speak to each in just a moment.
When we spoke on our first earnings call in August, we had just completed our direct listing, energized the first data hall at Ward County, and started collecting cash rent on the Nscale lease. Those milestones provide a strong cash-flowing foundation, and in the three months since, our conversations with prospective tenants have sharpened our view on what customers value most. When customers choose a site today, we believe they are weighing three things: whether the power will be there on time, whether the developer is reliable, and increasingly, the strength of the developer's balance sheet. We believe Ionic offers all three. Before moving on, I'd like to spend a moment on what we've seen in the market since August. Demand for AI capacity remains strong, but this quarter, we began to see how far apart announcing capacity and energizing it can be.
Power timelines have moved on a number of projects, and ERCOT's process has pushed tenants to look much harder at which sites have a real path to power. We believe that scrutiny works in our favor. Our 466 MW request at Ward County received provisional classification under Baseload Pathway (b) in ERCOT's Batch Zero process, and our Midland sites are already energized. At Ward County, we already have 323 gross megawatts under contract with Nscale, and beyond that, we have a pipeline of approximately 500 gross megawatts of near-term grid power to bring to market across Ward County and Midland. We also have the flexibility to fund this development with a debt-free balance sheet, approximately $630 million of liquidity, and a financeable cash-flowing lease on 234 MW, with a lease guaranteed by NVIDIA for the first five years and Microsoft as the ultimate customer.
Lastly, we've built a team with decades of experience designing, developing, and contracting data centers. Today's leading GPU platforms are pushing power densities into the hundreds of kilowatts per rack range and moving to direct-to-chip liquid cooling. Our development team brings deep mechanical and electrical engineering expertise, along with hands-on experience delivering and operating mission-critical facilities, and we're leveraging that experience to anticipate and manage risk. Turning now to the landscape in Texas. Yesterday's election brings a new administration to Austin in January. The governor-elect has said she intends to pause new data centers until the legislature sets new rules. We don't know yet what exactly that will look like. What we do know is where our project sits. As I mentioned, ERCOT provisionally classified our Ward County expansion as Baseload Pathway (b).
That pathway is for existing projects that have already achieved initial energization, and that distinction could help set us apart from new projects. We executed an agreement with our TSP in 2021 for 700 MW. It's been carried in transmission planning projects since 2023, and our TSP has since made transmission upgrades to its system, partially underwritten by our 700 MW. Advancing our project would ensure those investments are recovered as planned rather than burdening other ratepayers. We'll work constructively with the incoming administration, the legislature, and local officials as the rules get written, as we continue to support the responsible development of data centers in Texas. Of the incremental capacity expected at Ward, 89 MW are already contracted with Nscale, which will add a full-year run rate GAAP revenue of $72 million at triple net terms when the power is delivered.
That leaves 377 gross megawatts available for development at Ward. We've already had numerous conversations with interested customers, and in the coming weeks, we plan to launch a formal targeted marketing process for that capacity. As we've previously disclosed, Nscale holds a right of first refusal on this capacity. However, I want to be clear, it is a right of first refusal, not a call option, and it doesn't lock us into a specific price. Nscale can retain the capacity only by meeting or exceeding every term of the best offer we receive. Before ERCOT's verification process began, we had expected our marketing process to be a little further along. While the audit has shifted the timeline a bit, we have not slowed down on pre-development work, including test fits and vendor planning. That work allows us to move quickly once a contract is signed.
Our vision has always been to develop Ward County into a high-performance data center campus with high-quality counterparties. Turning to Midland, we have four sites with 112 MW of energized grid power today, ranging from 12 to 50 MW each. With immediate access to power and a variety of capacities, we believe this opens these sites to a broader set of customers with a wider range of use cases. Most of our work at Midland this year has been around the land itself, preparing each site to support a long-term data center development rather than a mining operation. We've made meaningful progress, and based on our conversations with prospective tenants, we still expect to move these sites off Bitcoin mining over the next six to 12 months. We'll continue to operate with urgency, but also with discipline. Available grid power in 2027 is scarce.
We believe taking the time to get the right counterparty on the right terms will create the most value for shareholders. That brings me to how we are evaluating these opportunities. We look at every opportunity the same way, the return on the capital we invest and the total value we can create relative to our cost of capital and the risk we take on. In assessing that risk, we look closely at the quality of the counterparty, the length and credit support of the contract, and protection against construction cost overruns. The structure we choose for each site is a big part of that equation. In a powered shell, as shown on page four of the latest investor presentation, we deliver the building and the power, and the tenant funds the fit-out.
In a turnkey or built-to-suit structure, we also deliver the mechanical, electrical, and plumbing in exchange for higher rent. We work collaboratively with our customers to turn high-level requirements into a verified fixed basis of design. If the customer still defines its needs, we start from reference designs we've already developed. Locking in the design before we build takes more time upfront, but it's one of the ways we reduce risk on schedule and cost. It's also why we've been deliberate about when we commit and what we announce. As customers, vendors, and partners look harder at the people behind the project, we believe that experience matters more today than ever. Our team has deep experience with both models, and being able to offer either one is an advantage in our conversations.
Finally, beyond Texas, our longer-term strategy is focused on developing sub-100 MW sites in and around major metros, where we expect inference and AI demand to grow. As AI moves from training models to running them, demand is shifting towards inference and agentic workloads. These workloads need different-sized data center developments, typically 25 to 75 MW, but in all cases, below the local utility's large load threshold. Many enterprise customers are also looking for sovereign solutions that keep proprietary data under their control. That's the market we intend to serve, and it's a natural extension of what the team has done for decades. Before I hand it to Chris, a brief word on shareholder engagement.
Engaging with our shareholders is an important part of how we run Ionic, and we believe we are well-aligned with them on our strategy to become a pure play, high-performance computing and AI data center developer, choosing the best risk-adjusted opportunities and successfully executing on them to maximize long-term value. Our board and management team share that focus, and it guides every capital allocation decision we make. Today, that means capturing the significant value we see in approximately 500 MW at Ward County and Midland that we expect to commercialize. As I wrap up, I come back to where I started. Our top priority is putting the remaining capacity at Ward County and Midland under contract, and the work we did this quarter moved us meaningfully closer to that.
FULL TRANSCRIPT
Continue the full translated transcript in StockNow.
Log in to unlock every statement, the English original, and speaker-by-speaker history.
Log in for the full transcriptCall participants
8 people spoke on this call — only 2 are shown here.
PARTICIPANT LIST
View participant details in StockNow.
Log in to see executives and analysts, their roles, and complete speaking history.
Log in to view all participantsKeep exploring